ITAC Assessment: UF0609
ITAC logo
ITAC Assessment: UF0609
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Metal & Rigid Plastic Tools
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 122,600
ft2
Annual Production 16,747,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $421,437 4,740,534
kWh
Electricity Demand $123,441 10,133
kW-mo/yr
Electricity Fees $14,388 -
Waste Disposal Costs
Water Usage $47,871 3,450
Tgal
TOTAL YEARLY COSTS $607,137
RECOMMENDED SAVINGS* $233,974 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.9114: Use solar heat to make electricty $104,116 $322,608 $57,333
644,189
kWh
$46,783
-
kW-mo/yr
- -
02 2.3191: Use demand controller or load shedder $38,174 $25,504 $29,533
331,837
kWh
$8,641
-
kW-mo/yr
- -
03 2.6231: Utilize controls to operate equipment only when needed $16,360 $25,380 $12,657
142,216
kWh
$3,703
-
kW-mo/yr
- -
04 2.4112: Install soft-start to eliminate nuisance trips $14,767 $40,488 $14,767
165,919
kWh
- - -
05 2.3212: Optimize plant power factor $3,546 $9,000 - - $3,546 -
06 4.662: Level one – add communication using iiot devices to existing control system to modify operations $35,940 - - - - $35,940
07 4.661: Level zero – install control systems for existing equipment $21,071 $25,000 $21,071
237,027
kWh
- - -
TOTAL RECOMMENDED $233,974 $447,980 $135,361
1,521,188
kWh
$59,127
-
kW-mo/yr
$3,546 $35,940
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs