| Assessment Year | 2011 |
|---|---|
| Principal Product | Soup |
| NAICS | 311991: Perishable Prepared Food Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 160 |
| Plant Area |
70,000
ft2
|
| Annual Production | 32,500,000
lb
|
| Production Hrs. Annual | 5,590
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $354,145 | 3,656,592 |
kWh
|
$0.097 |
| Electricity Demand | $200,568 | 9,230 |
kW-mo/yr
|
$21.73 |
| Electricity Fees | $45,492 | - |
|
- |
| Natural Gas | $368,022 | 34,596 |
MMBtu
|
$10.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $72,806 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2611: Moderate cooling tower outlet temperature | $47,869 | $10,650 |
$32,310
333,781
kWh
|
$15,559
-
kW-mo/yr
|
- | |
| 02 | 2.4131: Size electric motors for peak operating efficiency | $15,371 | $17,325 |
$9,548
98,646
kWh
|
$5,823
-
kW-mo/yr
|
- | |
| 03 | 2.2136: Install / repair insulation on steam lines | $4,256 | $8,190 | - | - |
$4,256
-
MMBtu
|
|
| 04 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $2,288 | $2,070 |
$1,600
16,524
kWh
|
$688
-
kW-mo/yr
|
- | |
| 05 | 2.2694: Use highest temperature for chilling or cold storage | $2,033 | $200 |
$1,425
14,722
kWh
|
$608
-
kW-mo/yr
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $496 | $700 |
$496
5,132
kWh
|
- | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $493 | $200 |
$493
5,090
kWh
|
- | - | |
| TOTAL RECOMMENDED | $72,806 | $39,335 |
$45,872
473,895
kWh
|
$22,678
-
kW-mo/yr
|
$4,256
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs