| Assessment Year | 2024 |
|---|---|
| Principal Product | Treated Wastewater |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $5 M to 10M |
| # of Employees | 24 |
| Plant Area |
8,000,000
ft2
|
| Annual Production | 16,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,144,605 | 27,149,953 |
kWh
|
$0.079 |
| Electricity Demand | $548,965 | 151,386 |
kW-mo/yr
|
$3.63 |
| Electricity Fees | $139,643 | - |
|
- |
| TOTAL YEARLY COSTS | $2,833,213 | |||
| RECOMMENDED SAVINGS* | $547,883 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $333,398 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $188,564 | $146,067 |
$150,139
1,900,496
kWh
|
$38,425
-
kW-mo/yr
|
- | - | |
| 02 | 2.9114: Use solar heat to make electricty | $65,322 | $322,608 |
$51,398
650,603
kWh
|
$13,924
-
kW-mo/yr
|
- | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $38,799 | $79,800 |
$33,017
417,939
kWh
|
$5,782
-
kW-mo/yr
|
- | - | |
| 04 | 2.6231: Utilize controls to operate equipment only when needed | $35,430 | $25,350 |
$35,430
448,486
kWh
|
- | - | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,283 | - |
$4,293
54,340
kWh
|
- | $416 | $574 | |
| 06 | 4.661: Level zero – install control systems for existing equipment | $214,485 | $60,000 |
$214,485
2,714,995
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $547,883 | $633,825 |
$488,762
6,186,859
kWh
|
$58,131
-
kW-mo/yr
|
$416 | $574 | ||
| TOTAL IMPLEMENTED | $333,398 | $573,825 |
$274,277
3,471,864
kWh
|
$58,131
-
kW-mo/yr
|
$416 | $574 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs