ITAC Assessment: UF0606
ITAC logo
ITAC Assessment: UF0606
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Treated Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $5
M
to 10
M
# of Employees 24
Plant Area 8,000,000
ft2
Annual Production 16,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,144,605 27,149,953
kWh
Electricity Demand $548,965 151,386
kW-mo/yr
Electricity Fees $139,643 -
TOTAL YEARLY COSTS $2,833,213
RECOMMENDED SAVINGS* $547,883 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $333,398

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
01 2.3191: Use demand controller or load shedder $188,564 $146,067 $150,139
1,900,496
kWh
$38,425
-
kW-mo/yr
- -
02 2.9114: Use solar heat to make electricty $65,322 $322,608 $51,398
650,603
kWh
$13,924
-
kW-mo/yr
- -
03 2.4133: Use most efficient type of electric motors $38,799 $79,800 $33,017
417,939
kWh
$5,782
-
kW-mo/yr
- -
04 2.6231: Utilize controls to operate equipment only when needed $35,430 $25,350 $35,430
448,486
kWh
- - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $5,283 - $4,293
54,340
kWh
- $416 $574
06 4.661: Level zero – install control systems for existing equipment $214,485 $60,000 $214,485
2,714,995
kWh
- - -
TOTAL RECOMMENDED $547,883 $633,825 $488,762
6,186,859
kWh
$58,131
-
kW-mo/yr
$416 $574
TOTAL IMPLEMENTED $333,398 $573,825 $274,277
3,471,864
kWh
$58,131
-
kW-mo/yr
$416 $574
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs