ITAC Assessment: UF0597
ITAC logo
ITAC Assessment: UF0597
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Extruded Vinyl Rubber
NAICS 326299: All Other Rubber Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 25
Plant Area 91,000
ft2
Annual Production 23,601,102
lb
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $180,107 2,733,320
kWh
Electricity Demand $28,365 6,856
kW-mo/yr
Electricity Fees $43,186 -
Natural Gas $539 8
MMBtu
LPG $4,538 167
MMBtu
Waste Disposal Costs
Water Usage $3,584 979
Tgal
TOTAL YEARLY COSTS $260,319
RECOMMENDED SAVINGS* $144,650 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $144,650

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.3191: Use demand controller or load shedder $20,876 $14,705 $18,040
273,332
kWh
$2,836
-
kW-mo/yr
-
02 2.4133: Use most efficient type of electric motors $11,736 $15,722 $8,283
125,502
kWh
$3,453
-
kW-mo/yr
-
03 2.6231: Utilize controls to operate equipment only when needed $9,612 $25,370 $9,612
145,643
kWh
- -
04 2.2622: Replace existing chiller with high efficiency model $6,142 $22,000 $4,764
72,176
kWh
$1,378
-
kW-mo/yr
-
05 2.4112: Install soft-start to eliminate nuisance trips $3,959 $11,134 $3,959
59,990
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,382 $13,706 $2,874
43,547
kWh
$508
-
kW-mo/yr
-
07 2.7135: Install occupancy sensors $1,699 $4,994 $1,699
25,745
kWh
- -
08 4.513: Re-arrange equipment layout to reduce labor costs $51,744 $18,218 - - $51,744
09 4.424: Improve space comfort conditioning $35,500 $4,261 $(-4,337.0)
(-65,707)
kWh
$(-523.0)
-
kW-mo/yr
$40,360
TOTAL RECOMMENDED $144,650 $130,110 $44,894
680,228
kWh
$7,652
-
kW-mo/yr
$92,104
TOTAL IMPLEMENTED $144,650 $130,110 $44,894
680,228
kWh
$7,652
-
kW-mo/yr
$92,104
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs