ITAC Assessment: UF0594
ITAC logo
ITAC Assessment: UF0594
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Injection Molded PLastic Products
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 30
Plant Area 69,000
ft2
Annual Production 782,000
lb
Production Hrs. Annual 7,345
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $115,663 1,790,000
kWh
Electricity Demand $54,388 4,576
kW-mo/yr
Electricity Fees $15,324 -
TOTAL YEARLY COSTS $185,375
RECOMMENDED SAVINGS* $163,213 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,099

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.9114: Use solar heat to make electricty $87,918 $289,896 $42,280
650,469
kWh
$45,638
-
kW-mo/yr
-
02 2.4311: Recover mechanical energy $19,952 $159 $(-485.0)
(-7,460)
kWh
- $20,437
03 2.3191: Use demand controller or load shedder $17,069 $9,630 $11,635
179,000
kWh
$5,434
-
kW-mo/yr
-
04 2.3141: Use battery storage for demand control $15,924 $16,616 $(-650.0)
(-10,000)
kWh
$(-1,426.0)
-
kW-mo/yr
$18,000
05 2.4133: Use most efficient type of electric motors $6,320 $18,243 $4,833
74,361
kWh
$1,487
-
kW-mo/yr
-
06 2.6231: Utilize controls to operate equipment only when needed $5,148 $25,265 $5,148
79,200
kWh
- -
07 2.7425: Clean or color roof to reduce solar load $3,181 $6,536 $3,181
48,940
kWh
- -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,918 $756 $2,918
44,898
kWh
- -
09 2.4112: Install soft-start to eliminate nuisance trips $1,390 $4,885 $1,390
21,384
kWh
- -
10 4.424: Improve space comfort conditioning $3,393 $1,754 $(-1,282.0)
(-19,721)
kWh
$(-751.0)
-
kW-mo/yr
$5,426
TOTAL RECOMMENDED $163,213 $373,740 $68,968
1,061,071
kWh
$50,382
-
kW-mo/yr
$43,863
TOTAL IMPLEMENTED $6,099 $7,292 $6,099
93,838
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs