ITAC Assessment: NC0174
ITAC logo
ITAC Assessment: NC0174
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Recycled paper products
NAICS
n/a
SIC 2621: Paper Mills
Sales Range $50
M
to 100
M
# of Employees 92
Plant Area 350,000
ft2
Annual Production 29,200,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $448,440 19,088,218
kWh
Electricity Demand $497,808 31,126
kW-mo/yr
Electricity Fees $4,105 -
Natural Gas $478,481 132,995
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,747 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,992

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4226: Use / purchase optimum sized compressor $9,777 $2,000 $5,331
226,846
kWh
$4,446
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $504 $150 $282
11,430
kWh
$222
-
kW-mo/yr
-
03 2.1133: Adjust burners for efficient operation $858 $700 - - $858
-
MMBtu
04 2.2511: Insulate bare equipment $1,535 $1,006 - - $1,535
-
MMBtu
05 2.2437: Recover waste heat from equipment $22,630 $13,000 - - $22,630
-
MMBtu
06 2.7111: Reduce illumination to minimum necessary levels $3,443 $3,520 $1,713
72,978
kWh
$1,730
-
kW-mo/yr
-
TOTAL RECOMMENDED $38,747 $20,376 $7,326
311,254
kWh
$6,398
-
kW-mo/yr
$25,023
-
MMBtu
TOTAL IMPLEMENTED $23,992 $13,850 $282
11,430
kWh
$222
-
kW-mo/yr
$23,488
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs