Assessment Year | 2023 |
---|---|
Principal Product | Bread |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 25 |
Plant Area |
256,000
ft2
|
Annual Production | 36,605
ton
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $800,718 | 11,212,200 |
kWh
|
$0.071 | |
Electricity Demand | $215,574 | 22,507 |
kW-mo/yr
|
$9.58 | |
Electricity Fees | $162,622 | - |
|
- | |
Natural Gas | $505,312 | 60,931 |
MMBtu
|
$8.29 | |
Waste Disposal Costs | |||||
Water Usage | $52,286 | 11,570 |
Tgal
|
$4.52 | |
TOTAL YEARLY COSTS | $1,736,512 | ||||
RECOMMENDED SAVINGS* | $343,230 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $242,066 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $101,164 | $60,322 |
$79,607
1,121,220
kWh
|
$21,557
-
kW-mo/yr
|
- | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $90,544 | $67,849 |
$90,544
1,275,264
kWh
|
- | - | - | - | |
03 | 2.4112: Install soft-start to eliminate nuisance trips | $16,705 | $11,574 |
$16,705
235,289
kWh
|
- | - | - | - | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $31,115 | $12,420 |
$(-514.0)
(-7,245)
kWh
|
$(-403.0)
-
kW-mo/yr
|
- | - | $32,032 | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $10,955 | $25,440 |
$10,955
154,295
kWh
|
- | - | - | - | |
06 | 2.8117: Install sub-metering equipment | $10,106 | $11,100 | - | - |
$10,106
-
MMBtu
|
- | - | |
07 | 2.2135: Repair and eliminate steam leaks | $3,034 | $528 | - | - |
$2,877
-
MMBtu
|
$157
-
Tgal
|
- | |
08 | 4.661: Level zero – install control systems for existing equipment | $79,607 | $10,000 |
$79,607
1,121,200
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $343,230 | $199,233 |
$276,904
3,900,023
kWh
|
$21,154
-
kW-mo/yr
|
$12,983
-
MMBtu
|
$157
-
Tgal
|
$32,032 | ||
TOTAL IMPLEMENTED | $242,066 | $138,911 |
$197,297
2,778,803
kWh
|
$(-403.0)
-
kW-mo/yr
|
$12,983
-
MMBtu
|
$157
-
Tgal
|
$32,032 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs