Assessment Year | 2023 |
---|---|
Principal Product | Ophthalmic Medication |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
175,677
ft2
|
Annual Production | 65,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $885,582 | 17,794,789 |
kWh
|
$0.050 | |
Electricity Demand | $414,289 | 30,331 |
kW-mo/yr
|
$13.66 | |
Electricity Fees | $214,588 | - |
|
- | |
Natural Gas | $159,004 | 57,394 |
MMBtu
|
$2.77 | |
Waste Disposal Costs | |||||
Water Usage | $229,502 | 43,226 |
Tgal
|
$5.31 | |
Water Disposal | $227,118 | 43,226 |
Tgal
|
$5.25 | |
TOTAL YEARLY COSTS | $2,130,083 | ||||
RECOMMENDED SAVINGS* | $1,840,708 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,710,305 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $920,434 | $2,793,000 |
$889,739
17,794,789
kWh
|
$344,207
-
kW-mo/yr
|
- |
$(-327,887.0)
-
MMBtu
|
$14,375 | |
02 | 2.3113: Make ice during off peak hours for cooling | $505,092 | $2,115,660 |
$306,633
6,132,668
kWh
|
- | $198,459 | - | - | |
03 | 2.3191: Use demand controller or load shedder | $130,403 | $95,736 |
$88,974
1,779,479
kWh
|
$41,429
-
kW-mo/yr
|
- | - | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $71,810 | $25,340 |
$71,810
1,436,203
kWh
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $42,787 | $43,077 |
$30,363
607,262
kWh
|
$12,424
-
kW-mo/yr
|
- | - | - | |
06 | 2.5122: Replace high resistance ducts, pipes, and fittings | $18,200 | $14,400 |
$18,200
364,000
kWh
|
- | - | - | - | |
07 | 2.2615: Clean condenser tubes | $15,589 | - |
$15,589
311,786
kWh
|
- | - | - | - | |
08 | 2.1213: Direct warmest air to combustion intake | $13,274 | $30,000 | - | - | - |
$13,274
-
MMBtu
|
- | |
09 | 2.4239: Eliminate or reduce compressed air usage | $5,438 | - |
$5,438
108,767
kWh
|
- | - | - | - | |
10 | 2.7245: Use direct air supply to exhaust hoods | $5,304 | $4,300 |
$5,304
106,071
kWh
|
- | - | - | - | |
11 | 2.1113: Reduce combustion air flow to optimum | $4,770 | $2,800 | - | - | - |
$4,770
-
MMBtu
|
- | |
12 | 2.1222: Install turbulators | $4,595 | $7,500 | - | - | - |
$4,595
-
MMBtu
|
- | |
13 | 2.7273: Install desiccant humidity control system | $4,532 | $754 |
$4,532
90,639
kWh
|
- | - | - | - | |
14 | 2.7233: Use properly designed and sized hvac equipment | $4,316 | $3,069 |
$4,316
86,326
kWh
|
- | - | - | - | |
15 | 2.7135: Install occupancy sensors | $2,868 | $9,968 |
$2,868
57,363
kWh
|
- | - | - | - | |
16 | 2.7272: Install heat pipes / raise cooling setpoint | $2,322 | - |
$2,322
46,443
kWh
|
- | - | - | - | |
17 | 4.661: Level zero – install control systems for existing equipment | $88,974 | $10,000 |
$88,974
1,779,479
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $1,840,708 | $5,155,604 |
$1,535,062
30,701,275
kWh
|
$398,060
-
kW-mo/yr
|
$198,459 |
$(-305,248.0)
-
MMBtu
|
$14,375 | ||
TOTAL IMPLEMENTED | $1,710,305 | $5,059,868 |
$1,446,088
28,921,796
kWh
|
$356,631
-
kW-mo/yr
|
$198,459 |
$(-305,248.0)
-
MMBtu
|
$14,375 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs