ITAC Assessment: UF0589
ITAC logo
ITAC Assessment: UF0589
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Ophthalmic Medication
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 175,677
ft2
Annual Production 65,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $885,582 17,794,789
kWh
Electricity Demand $414,289 30,331
kW-mo/yr
Electricity Fees $214,588 -
Natural Gas $159,004 57,394
MMBtu
Waste Disposal Costs
Water Usage $229,502 43,226
Tgal
Water Disposal $227,118 43,226
Tgal
TOTAL YEARLY COSTS $2,130,083
RECOMMENDED SAVINGS* $1,840,708 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,710,305

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $920,434 $2,793,000 $889,739
17,794,789
kWh
$344,207
-
kW-mo/yr
- $(-327,887.0)
-
MMBtu
$14,375
02 2.3113: Make ice during off peak hours for cooling $505,092 $2,115,660 $306,633
6,132,668
kWh
- $198,459 - -
03 2.3191: Use demand controller or load shedder $130,403 $95,736 $88,974
1,779,479
kWh
$41,429
-
kW-mo/yr
- - -
04 2.6231: Utilize controls to operate equipment only when needed $71,810 $25,340 $71,810
1,436,203
kWh
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $42,787 $43,077 $30,363
607,262
kWh
$12,424
-
kW-mo/yr
- - -
06 2.5122: Replace high resistance ducts, pipes, and fittings $18,200 $14,400 $18,200
364,000
kWh
- - - -
07 2.2615: Clean condenser tubes $15,589 - $15,589
311,786
kWh
- - - -
08 2.1213: Direct warmest air to combustion intake $13,274 $30,000 - - - $13,274
-
MMBtu
-
09 2.4239: Eliminate or reduce compressed air usage $5,438 - $5,438
108,767
kWh
- - - -
10 2.7245: Use direct air supply to exhaust hoods $5,304 $4,300 $5,304
106,071
kWh
- - - -
11 2.1113: Reduce combustion air flow to optimum $4,770 $2,800 - - - $4,770
-
MMBtu
-
12 2.1222: Install turbulators $4,595 $7,500 - - - $4,595
-
MMBtu
-
13 2.7273: Install desiccant humidity control system $4,532 $754 $4,532
90,639
kWh
- - - -
14 2.7233: Use properly designed and sized hvac equipment $4,316 $3,069 $4,316
86,326
kWh
- - - -
15 2.7135: Install occupancy sensors $2,868 $9,968 $2,868
57,363
kWh
- - - -
16 2.7272: Install heat pipes / raise cooling setpoint $2,322 - $2,322
46,443
kWh
- - - -
17 4.661: Level zero – install control systems for existing equipment $88,974 $10,000 $88,974
1,779,479
kWh
- - - -
TOTAL RECOMMENDED $1,840,708 $5,155,604 $1,535,062
30,701,275
kWh
$398,060
-
kW-mo/yr
$198,459 $(-305,248.0)
-
MMBtu
$14,375
TOTAL IMPLEMENTED $1,710,305 $5,059,868 $1,446,088
28,921,796
kWh
$356,631
-
kW-mo/yr
$198,459 $(-305,248.0)
-
MMBtu
$14,375
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs