Assessment Year | 2022 |
---|---|
Principal Product | Wastewater Treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $1 M to 5M |
# of Employees | 15 |
Plant Area |
1,314,968
ft2
|
Annual Production | 2,900,770
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $476,429 | 5,642,949 |
kWh
|
$0.084 |
Electricity Demand | $49,718 | 16,409 |
kW-mo/yr
|
$3.03 |
Electricity Fees | $47,566 | - |
|
- |
TOTAL YEARLY COSTS | $573,713 | |||
RECOMMENDED SAVINGS* | $705,047 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $649,622 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $42,152 | $105,185 |
$34,131
406,324
kWh
|
$8,021
-
kW-mo/yr
|
- | - | - | |
02 | 2.3191: Use demand controller or load shedder | $36,661 | $30,359 |
$33,181
395,006
kWh
|
$3,480
-
kW-mo/yr
|
- | - | - | |
03 | 2.4322: Use or replace with energy efficient substitutes | $13,557 | $36,000 |
$13,557
161,394
kWh
|
- | - | - | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $5,945 | $25,600 |
$5,945
70,776
kWh
|
- | - | - | - | |
05 | 2.7135: Install occupancy sensors | $5,294 | $10,558 |
$5,294
63,024
kWh
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,095 | $12,753 |
$4,637
55,202
kWh
|
$458
-
kW-mo/yr
|
- | - | - | |
07 | 2.3212: Optimize plant power factor | $2,079 | $5,093 | - | - | - | $2,079 | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,003 | - |
$2,003
18,373
kWh
|
- | - | - | - | |
09 | 4.661: Level zero – install control systems for existing equipment | $47,401 | $10,000 |
$47,401
564,295
kWh
|
- | - | - | - | |
10 | 4.662: Level one – add communication using iiot devices to existing control system to modify operations | $4,716 | - | - | - | - | $4,716 | - | |
11 | 3.5217: Reuse / recycle/ sell paper products | $540,144 | $53,000 |
$(-26,711.0)
(-317,988)
kWh
|
$(-1,320.0)
-
kW-mo/yr
|
$(-28,148.0)
-
MMBtu
|
- | $596,323 | |
TOTAL RECOMMENDED | $705,047 | $288,548 |
$119,438
1,416,406
kWh
|
$10,639
-
kW-mo/yr
|
$(-28,148.0)
-
MMBtu
|
$6,795 | $596,323 | ||
TOTAL IMPLEMENTED | $649,622 | $247,855 |
$66,092
781,335
kWh
|
$10,639
-
kW-mo/yr
|
$(-28,148.0)
-
MMBtu
|
$4,716 | $596,323 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs