Assessment Year | 2022 |
---|---|
Principal Product | Water Pumps |
NAICS | 333996: Fluid Power Pump and Motor Manufacturing |
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $10 M to 50M |
# of Employees | 15 |
Plant Area |
466,864
ft2
|
Annual Production | 4,754
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $26,828 | 486,533 |
kWh
|
$0.055 | |
Electricity Demand | $21,912 | 2,003 |
kW-mo/yr
|
$10.94 | |
Electricity Fees | $10,768 | - |
|
- | |
Natural Gas | $1,071 | 120 |
MMBtu
|
$8.95 | |
LPG | $7,351 | 209 |
MMBtu
|
$35.12 | |
Fuel Oil #1 | $33,633 | 1,806 |
MMBtu
|
$18.62 | |
Waste Disposal Costs | |||||
Solid Waste (non-haz) | $15,600 | 915,931 |
lb
|
$0.017 | |
TOTAL YEARLY COSTS | $117,163 | ||||
RECOMMENDED SAVINGS* | $54,730 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $48,913 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $5,354 | $640 |
$2,739
49,804
kWh
|
$2,615
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.3191: Use demand controller or load shedder | $3,407 | $2,618 |
$1,873
34,057
kWh
|
$1,534
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.6242: Minimize operation of equipment maintained in standby condition | $3,363 | - | - | - |
$3,363
-
MMBtu
|
- | - | - | |
04 | 2.4226: Use / purchase optimum sized compressor | $3,190 | $15,730 |
$1,632
29,679
kWh
|
$1,558
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,991 | $304 |
$1,991
36,200
kWh
|
- | - | - | - | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $1,972 | - |
$1,972
35,862
kWh
|
- | - | - | - | - | |
07 | 2.7141: Lower light fixtures in high ceiling areas | $1,440 | $3,987 |
$802
14,580
kWh
|
$638
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7135: Install occupancy sensors | $1,187 | $4,373 |
$1,187
21,577
kWh
|
- | - | - | - | - | |
09 | 2.7425: Clean or color roof to reduce solar load | $1,049 | $200 |
$1,049
19,078
kWh
|
- | - | - | - | - | |
10 | 4.311: Schedule deliveries according to demand | $3,120 | $2,528 | - | - | - | - | $3,120 | - | |
11 | 3.5311: Recover and reuse waste material | $28,657 | $31,000 |
$(-386.0)
(-7,020)
kWh
|
$(-5,906.5)
-
kW-mo/yr
|
- |
$15,600
-
lb
|
- | $19,349 | |
TOTAL RECOMMENDED | $54,730 | $61,380 |
$12,859
233,817
kWh
|
$439
-
kW-mo/yr
|
$3,363
-
MMBtu
|
$15,600
-
lb
|
$3,120 | $19,349 | ||
TOTAL IMPLEMENTED | $48,913 | $37,290 |
$9,238
167,981
kWh
|
$(-1,757.1)
-
kW-mo/yr
|
$3,363
-
MMBtu
|
$15,600
-
lb
|
$3,120 | $19,349 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs