Assessment Year | 2022 |
---|---|
Principal Product | Bread |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $50 M to 100M |
# of Employees | 15 |
Plant Area |
125,000
ft2
|
Annual Production | 31,443
ton
|
Production Hrs. Annual | 7,748
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $440,610 | 8,521,765 |
kWh
|
$0.052 | |
Electricity Demand | $104,181 | 15,009 |
kW-mo/yr
|
$6.94 | |
Electricity Fees | $84,381 | - |
|
- | |
Natural Gas | $116,215 | 55,248 |
MMBtu
|
$2.10 | |
Waste Disposal Costs | |||||
Water Usage | $21,211 | 7,464 |
Tgal
|
$2.84 | |
Water Disposal | $52,078 | 10,504 |
Tgal
|
$4.96 | |
TOTAL YEARLY COSTS | $818,676 | ||||
RECOMMENDED SAVINGS* | $503,154 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $496,452 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $57,729 | $322,608 |
$31,079
597,668
kWh
|
$26,650
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 2.3191: Use demand controller or load shedder | $38,315 | $45,847 |
$31,019
596,524
kWh
|
$7,296
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.7243: Improve air circulation with destratification fans / other methods | $22,318 | $12,420 |
$(-1,414.0)
(-27,200)
kWh
|
$(-292.0)
-
kW-mo/yr
|
- | - | - | - | - | - | $24,024 | |
04 | 2.4133: Use most efficient type of electric motors | $13,484 | $20,340 |
$10,410
200,187
kWh
|
$3,074
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,896 | $25,258 |
$6,451
124,057
kWh
|
$1,445
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
06 | 2.6127: Maintain air filters by cleaning or replacement | $5,512 | $600 |
$1,288
24,762
kWh
|
- | - | - | - | $4,224 | - | - | - | |
07 | 2.3212: Optimize plant power factor | $5,422 | $24,763 | - | - | - | - | - | - | - | $5,422 | - | |
08 | 2.7425: Clean or color roof to reduce solar load | $3,103 | $14,366 |
$3,103
59,669
kWh
|
- | - | - | - | - | - | - | - | |
09 | 2.1222: Install turbulators | $2,101 | $7,500 | - | - |
$2,101
-
MMBtu
|
- | - | - | - | - | - | |
10 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,498 | $7,375 | - | - |
$1,498
-
MMBtu
|
- | - | - | - | - | - | |
11 | 4.662: Level one – add communication using iiot devices to existing control system to modify operations | $287,926 | - | - | - | - | - | - | - | - | - | $287,926 | |
12 | 4.661: Level zero – install control systems for existing equipment | $22,157 | - |
$22,157
426,088
kWh
|
- | - | - | - | - | - | - | - | |
13 | 4.114: Add/modify equipment to improve drying process | $16,503 | $80,000 |
$1,835
35,290
kWh
|
$6,308
-
kW-mo/yr
|
- | - | - | $8,360 | - | - | - | |
14 | 3.4131: Minimize contamination of water before treatment | $18,108 | $45,538 | - | - | - |
$7,323
-
Tgal
|
$12,791
-
Tgal
|
$(-1,100.0) | $(-906.0) | - | - | |
15 | 3.4154: Eliminate leaks in water lines and valves | $1,082 | $88 | - | - | - |
$394
-
Tgal
|
$688
-
Tgal
|
- | - | - | - | |
TOTAL RECOMMENDED | $503,154 | $606,703 |
$105,928
2,037,045
kWh
|
$44,481
-
kW-mo/yr
|
$3,599
-
MMBtu
|
$7,717
-
Tgal
|
$13,479
-
Tgal
|
$11,484 | $(-906.0) | $5,422 | $311,950 | ||
TOTAL IMPLEMENTED | $496,452 | $577,462 |
$102,825
1,977,376
kWh
|
$44,481
-
kW-mo/yr
|
- |
$7,717
-
Tgal
|
$13,479
-
Tgal
|
$11,484 | $(-906.0) | $5,422 | $311,950 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs