ITAC Assessment: UF0574
ITAC logo
ITAC Assessment: UF0574
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Bread
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $50
M
to 100
M
# of Employees 15
Plant Area 125,000
ft2
Annual Production 31,443
ton
Production Hrs. Annual 7,748
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $440,610 8,521,765
kWh
Electricity Demand $104,181 15,009
kW-mo/yr
Electricity Fees $84,381 -
Natural Gas $116,215 55,248
MMBtu
Waste Disposal Costs
Water Usage $21,211 7,464
Tgal
Water Disposal $52,078 10,504
Tgal
TOTAL YEARLY COSTS $818,676
RECOMMENDED SAVINGS* $503,154 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $496,452

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.9114: Use solar heat to make electricty $57,729 $322,608 $31,079
597,668
kWh
$26,650
-
kW-mo/yr
- - - - - - -
02 2.3191: Use demand controller or load shedder $38,315 $45,847 $31,019
596,524
kWh
$7,296
-
kW-mo/yr
- - - - - - -
03 2.7243: Improve air circulation with destratification fans / other methods $22,318 $12,420 $(-1,414.0)
(-27,200)
kWh
$(-292.0)
-
kW-mo/yr
- - - - - - $24,024
04 2.4133: Use most efficient type of electric motors $13,484 $20,340 $10,410
200,187
kWh
$3,074
-
kW-mo/yr
- - - - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $7,896 $25,258 $6,451
124,057
kWh
$1,445
-
kW-mo/yr
- - - - - - -
06 2.6127: Maintain air filters by cleaning or replacement $5,512 $600 $1,288
24,762
kWh
- - - - $4,224 - - -
07 2.3212: Optimize plant power factor $5,422 $24,763 - - - - - - - $5,422 -
08 2.7425: Clean or color roof to reduce solar load $3,103 $14,366 $3,103
59,669
kWh
- - - - - - - -
09 2.1222: Install turbulators $2,101 $7,500 - - $2,101
-
MMBtu
- - - - - -
10 2.7447: Install vinyl strip / high speed / air curtain doors $1,498 $7,375 - - $1,498
-
MMBtu
- - - - - -
11 4.662: Level one – add communication using iiot devices to existing control system to modify operations $287,926 - - - - - - - - - $287,926
12 4.661: Level zero – install control systems for existing equipment $22,157 - $22,157
426,088
kWh
- - - - - - - -
13 4.114: Add/modify equipment to improve drying process $16,503 $80,000 $1,835
35,290
kWh
$6,308
-
kW-mo/yr
- - - $8,360 - - -
14 3.4131: Minimize contamination of water before treatment $18,108 $45,538 - - - $7,323
-
Tgal
$12,791
-
Tgal
$(-1,100.0) $(-906.0) - -
15 3.4154: Eliminate leaks in water lines and valves $1,082 $88 - - - $394
-
Tgal
$688
-
Tgal
- - - -
TOTAL RECOMMENDED $503,154 $606,703 $105,928
2,037,045
kWh
$44,481
-
kW-mo/yr
$3,599
-
MMBtu
$7,717
-
Tgal
$13,479
-
Tgal
$11,484 $(-906.0) $5,422 $311,950
TOTAL IMPLEMENTED $496,452 $577,462 $102,825
1,977,376
kWh
$44,481
-
kW-mo/yr
- $7,717
-
Tgal
$13,479
-
Tgal
$11,484 $(-906.0) $5,422 $311,950
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs