| Assessment Year | 2021 |
|---|---|
| Principal Product | Paper, Paperboard and Fresh-house Cartons |
| NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
| SIC | 2671: Packaging Paper and Plastics Film, Coated and Laminated |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
300,000
ft2
|
| Annual Production | 11,500,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $347,467 | 13,826,787 |
kWh
|
$0.025 |
| Electricity Demand | $119,707 | 30,229 |
kW-mo/yr
|
$3.96 |
| Electricity Fees | $379,396 | - |
|
- |
| Natural Gas | $65,759 | 18,454 |
MMBtu
|
$3.56 |
| TOTAL YEARLY COSTS | $912,329 | |||
| RECOMMENDED SAVINGS* | $141,818 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $133,264 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $34,350 | $150,000 |
$34,350
1,374,000
kWh
|
- | |
| 02 | 2.4133: Use most efficient type of electric motors | $33,993 | $25,529 |
$25,479
1,019,157
kWh
|
$8,514
-
kW-mo/yr
|
|
| 03 | 2.2622: Replace existing chiller with high efficiency model | $33,607 | $165,000 |
$23,375
935,000
kWh
|
$10,232
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,904 | $455 |
$8,904
356,152
kWh
|
- | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,870 | $8,850 |
$8,870
354,801
kWh
|
- | |
| 06 | 2.4112: Install soft-start to eliminate nuisance trips | $8,554 | $38,357 |
$8,554
342,145
kWh
|
- | |
| 07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,282 | $25,340 |
$7,282
291,271
kWh
|
- | |
| 08 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $3,710 | $5,998 |
$3,710
148,387
kWh
|
- | |
| 09 | 2.4224: Upgrade controls on compressors | $2,548 | $2,336 |
$2,548
101,928
kWh
|
- | |
| TOTAL RECOMMENDED | $141,818 | $421,865 |
$123,072
4,922,841
kWh
|
$18,746
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $133,264 | $383,508 |
$114,518
4,580,696
kWh
|
$18,746
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs