Assessment Year | 2020 |
---|---|
Principal Product | Half & Half and Creams |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2024: Ice Cream and Frozen Desserts |
Sales Range | $50 M to 100M |
# of Employees | 50 |
Plant Area |
170,000
ft2
|
Annual Production | 65,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,016,692 | 11,086,805 |
kWh
|
$0.092 | |
Natural Gas | $502,190 | 156,878 |
MMBtu
|
$3.20 | |
Waste Disposal Costs | |||||
Water Usage | $50,000 | 25,000 |
Tgal
|
$2.00 | |
Other Liquid (non-haz) | $205,485 | 587,099 |
gal
|
$0.35 | |
TOTAL YEARLY COSTS | $1,774,367 | ||||
RECOMMENDED SAVINGS* | $1,676,185 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,658,034 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.9141: Install anaerobic digester | $1,032,365 | $4,965,000 | - |
$527,518
-
MMBtu
|
$291,200
-
gal
|
- | - | $213,647 | |
02 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $537,853 | $1,400,000 |
$782,000
8,500,000
kWh
|
$(-159,147.0)
-
MMBtu
|
- | $(-85,000.0) | - | - | |
03 | 2.2437: Recover waste heat from equipment | $62,520 | $30,000 | - |
$62,520
-
MMBtu
|
- | - | - | - | |
04 | 2.1222: Install turbulators | $18,151 | $7,500 | - |
$18,151
-
MMBtu
|
- | - | - | - | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $14,189 | $1,500 |
$14,189
154,223
kWh
|
- | - | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $6,254 | $4,938 |
$6,254
67,983
kWh
|
- | - | - | - | - | |
07 | 2.2136: Install / repair insulation on steam lines | $2,687 | $1,936 | - |
$2,687
-
MMBtu
|
- | - | - | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,166 | - |
$1,662
18,069
kWh
|
- | - | $298 | $206 | - | |
TOTAL RECOMMENDED | $1,676,185 | $6,410,874 |
$804,105
8,740,275
kWh
|
$451,729
-
MMBtu
|
$291,200
-
gal
|
$(-84,702.0) | $206 | $213,647 | ||
TOTAL IMPLEMENTED | $1,658,034 | $6,403,374 |
$804,105
8,740,275
kWh
|
$433,578
-
MMBtu
|
$291,200
-
gal
|
$(-84,702.0) | $206 | $213,647 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs