| Assessment Year | 2019 |
|---|---|
| Principal Product | Organic Silicone Intermediates |
| NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
| SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
871,200
ft2
|
| Annual Production | 5,300
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,167,286 | 13,525,200 |
kWh
|
$0.086 |
| Electricity Demand | $213,798 | 21,928 |
kW-mo/yr
|
$9.75 |
| Electricity Fees | $255,342 | - |
|
- |
| Natural Gas | $279,549 | 42,192 |
MMBtu
|
$6.63 |
| TOTAL YEARLY COSTS | $1,915,975 | |||
| RECOMMENDED SAVINGS* | $451,978 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $446,058 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $365,719 | $1,800,000 |
$753,360
8,760,000
kWh
|
$117,000
-
kW-mo/yr
|
$(-565,841.0)
-
MMBtu
|
$61,200 | |
| 02 | 2.4133: Use most efficient type of electric motors | $40,964 | $16,606 |
$33,359
387,896
kWh
|
$7,605
-
kW-mo/yr
|
- | - | |
| 03 | 2.6231: Utilize controls to operate equipment only when needed | $22,041 | $3,368 | - | - |
$22,041
-
MMBtu
|
- | |
| 04 | 2.2511: Insulate bare equipment | $11,463 | $2,551 | - | - |
$11,463
-
MMBtu
|
- | |
| 05 | 2.1222: Install turbulators | $5,920 | $7,500 | - | - |
$5,920
-
MMBtu
|
- | |
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,871 | $1,550 | - | - |
$5,871
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $451,978 | $1,831,575 |
$786,719
9,147,896
kWh
|
$124,605
-
kW-mo/yr
|
$(-520,546.0)
-
MMBtu
|
$61,200 | ||
| TOTAL IMPLEMENTED | $446,058 | $1,824,075 |
$786,719
9,147,896
kWh
|
$124,605
-
kW-mo/yr
|
$(-526,466.0)
-
MMBtu
|
$61,200 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs