ITAC Assessment: UF0524
ITAC logo
ITAC Assessment: UF0524
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Rigid Plastics
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 180
Plant Area 498,000
ft2
Annual Production 178,358,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $4,364,349 68,538,115
kWh
Electricity Demand $984,019 120,164
kW-mo/yr
Electricity Fees $490,809 -
Natural Gas $350,000 100,000
MMBtu
Waste Disposal Costs
Water Usage $7,493 3,022
Tgal
Water Disposal $17,615 3,724
Tgal
TOTAL YEARLY COSTS $6,214,285
RECOMMENDED SAVINGS* $727,479 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $96,820

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $371,464 $1,750,000 $560,640
8,760,000
kWh
$98,268
-
kW-mo/yr
$(-182,324.0)
-
MMBtu
- - $(-105,120.0) -
02 2.4322: Use or replace with energy efficient substitutes $212,420 $75,000 $158,078
2,345,375
kWh
$54,342
-
kW-mo/yr
- - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $62,330 $139,780 $50,214
784,601
kWh
$12,116
-
kW-mo/yr
- - - - -
04 2.4222: Install adequate dryers on air lines to eliminate blowdown $22,663 $18,928 $22,663
354,117
kWh
- - - - - -
05 2.7491: Insulate glazing, walls, ceilings, and roofs $19,167 $89,865 $19,167
299,480
kWh
- - - - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,978 $400 $9,978
112,109
kWh
- - - - - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $6,897 - $6,707
104,801
kWh
- - - $81 - $109
08 2.2522: Isolate hot or cold equipment $4,945 $5,090 $4,945
77,263
kWh
- - - - - -
09 3.4113: Treat and reuse rinse waters $17,615 - - - - $17,615
-
Tgal
- - -
TOTAL RECOMMENDED $727,479 $2,079,063 $832,392
12,837,746
kWh
$164,726
-
kW-mo/yr
$(-182,324.0)
-
MMBtu
$17,615
-
Tgal
$81 $(-105,120.0) $109
TOTAL IMPLEMENTED $96,820 $140,180 $66,899
1,001,511
kWh
$12,116
-
kW-mo/yr
- $17,615
-
Tgal
$81 - $109
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs