Assessment Year | 2018 |
---|---|
Principal Product | Sports Garments - T-Shirts, Polo Shirts, Hoodies, etc. |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
250,000
ft2
|
Annual Production | 3,557,067
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $269,191 | 4,037,640 |
kWh
|
$0.067 |
Electricity Demand | $83,604 | 9,953 |
kW-mo/yr
|
$8.40 |
Electricity Fees | $73,873 | - |
|
- |
Natural Gas | $51,351 | 3,904 |
MMBtu
|
$13.15 |
TOTAL YEARLY COSTS | $478,018 | |||
RECOMMENDED SAVINGS* | $244,381 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,982 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $36,742 | $240,000 |
$(-3,057.0)
(-45,840)
kWh
|
$(-11,552.0)
-
kW-mo/yr
|
$51,351
-
MMBtu
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $87,600 | $7,358 | - | - | - | $87,600 | |
03 | 2.2437: Recover waste heat from equipment | $21,070 | $48,000 | - | - |
$21,070
-
MMBtu
|
- | |
04 | 2.6218: Turn off equipment when not in use | $10,267 | - | - | - |
$10,267
-
MMBtu
|
- | |
05 | 2.7145: Install skylights | $9,473 | $48,000 |
$9,473
142,029
kWh
|
- | - | - | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $5,837 | - |
$5,837
87,512
kWh
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,481 | $1,413 |
$4,674
70,080
kWh
|
$806
-
kW-mo/yr
|
- | - | |
08 | 2.7135: Install occupancy sensors | $4,644 | $797 |
$4,644
69,631
kWh
|
- | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,753 | $688 |
$2,753
41,276
kWh
|
- | - | - | |
10 | 4.112: Replace old machine with new automatic multi-station tool | $60,514 | $190,580 |
$(-1,402.0)
(-21,024)
kWh
|
$(-484.0)
-
kW-mo/yr
|
- | $62,400 | |
TOTAL RECOMMENDED | $244,381 | $536,836 |
$22,922
343,664
kWh
|
$(-11,229.6)
-
kW-mo/yr
|
$82,688
-
MMBtu
|
$150,000 | ||
TOTAL IMPLEMENTED | $28,982 | $2,898 |
$17,908
268,499
kWh
|
$806
-
kW-mo/yr
|
$10,267
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs