Assessment Year | 2011 |
---|---|
Principal Product | ammunition and pyrotechnics |
NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 280 |
Plant Area |
100,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 2,800
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $342,863 | 4,102,800 |
kWh
|
$0.084 |
Electricity Demand | $66,769 | 9,537 |
kW-mo/yr
|
$7.00 |
Natural Gas | $136,572 | 76,683 |
MMBtu
|
$1.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,806 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,603 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,739 | - |
$1,681
20,013
kWh
|
$782
-
kW-mo/yr
|
- | $420 | $2,856 | |
02 | 2.4225: Install common header on compressors | $8,773 | $222 |
$8,773
104,440
kWh
|
- | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,497 | - |
$3,381
40,261
kWh
|
$116
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,153 | $1,277 |
$1,153
11,417
kWh
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,440 | $3,310 |
$2,710
32,256
kWh
|
$730
-
kW-mo/yr
|
- | - | - | |
06 | 2.7124: Make a practice of turning off lights when not needed | $498 | - |
$498
5,928
kWh
|
- | - | - | - | |
07 | 2.2521: Isolate steam lines to avoid heating air conditioned areas | $1,379 | $1,140 | - | - |
$1,379
-
MMBtu
|
- | - | |
08 | 2.2515: Use optimum thickness insulation | $1,327 | $1,865 |
$1,327
13,140
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $25,806 | $7,814 |
$19,523
227,455
kWh
|
$1,628
-
kW-mo/yr
|
$1,379
-
MMBtu
|
$420 | $2,856 | ||
TOTAL IMPLEMENTED | $19,603 | $4,809 |
$14,815
174,054
kWh
|
$1,512
-
kW-mo/yr
|
- | $420 | $2,856 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs