| Assessment Year | 2010 |
|---|---|
| Principal Product | abrasive materials |
| NAICS | 327910: Abrasive Product Manufacturing |
| SIC | 3291: Abrasive Products |
| Sales Range | $100 M to 500M |
| # of Employees | 450 |
| Plant Area |
550,000
ft2
|
| Annual Production | 133,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,178,915 | 40,649,652 |
kWh
|
$0.054 |
| Natural Gas | $401,736 | 67,500 |
MMBtu
|
$5.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $374,425 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $22,343 | $1,105 |
$22,343
413,752
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $85,202 | $72,075 |
$85,201
1,577,799
kWh
|
$1
-
kW-mo/yr
|
- | |
| 03 | 2.7229: Air condition only space necessary | $15,093 | $1,615 |
$15,093
279,498
kWh
|
- | - | |
| 04 | 2.7229: Air condition only space necessary | $10,754 | $22,000 |
$10,754
199,143
kWh
|
- | - | |
| 05 | 2.7492: Use proper thickness of insulation on building envelope | $112,650 | $154,062 |
$112,650
2,086,103
kWh
|
- | - | |
| 06 | 2.4224: Upgrade controls on compressors | $24,615 | $975 |
$24,615
455,839
kWh
|
- | - | |
| 07 | 2.6218: Turn off equipment when not in use | $6,023 | $3,670 |
$6,023
111,529
kWh
|
- | - | |
| 08 | 2.4239: Eliminate or reduce compressed air usage | $1,272 | $2,160 |
$1,272
23,562
kWh
|
- | - | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $59,220 | $44,118 |
$59,220
1,096,072
kWh
|
- | - | |
| 10 | 2.2442: Preheat combustion air with waste heat | $14,054 | - | - | - |
$14,054
-
MMBtu
|
|
| 11 | 2.2113: Repair or replace steam traps | $14,482 | - | - | - |
$14,482
-
MMBtu
|
|
| 12 | 2.2442: Preheat combustion air with waste heat | $8,717 | - | - | - |
$8,717
-
MMBtu
|
|
| TOTAL RECOMMENDED | $374,425 | $301,780 |
$337,171
6,243,297
kWh
|
$1
-
kW-mo/yr
|
$37,253
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs