ITAC Assessment: TT0143
ITAC logo
ITAC Assessment: TT0143
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Heaters and Controls
NAICS 333414: Heating Equipment (except Warm Air Furnaces) Manufacturing
SIC 3433: Heating Equipment, Except Electric and Warm Air Furnaces
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 141,000
ft2
Annual Production 3,600
pieces
Production Hrs. Annual 4,125
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $238,202 3,583,200
kWh
Electricity Demand $93,378 7,921
kW-mo/yr
Electricity Fees $6,854 -
Natural Gas $36,782 3,748
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,988 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,401

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,223 $75 $827
12,521
kWh
$396
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,373 $3,000 $1,848
28,018
kWh
$525
-
kW-mo/yr
03 2.7122: Disconnect ballasts $214 $70 $172
2,606
kWh
$42
-
kW-mo/yr
04 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $2,178 $100 $1,002
15,182
kWh
$1,176
-
kW-mo/yr
TOTAL RECOMMENDED $5,988 $3,245 $3,849
58,327
kWh
$2,139
-
kW-mo/yr
TOTAL IMPLEMENTED $3,401 $175 $1,829
27,703
kWh
$1,572
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs