ITAC Assessment: UF0436
ITAC logo
ITAC Assessment: UF0436
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product xenograft and allograft products
NAICS 339113: Surgical Appliance and Supplies Manufacturing
SIC 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 133,072
ft2
Annual Production 465,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,440,093 14,966,519
kWh
Electricity Demand $208,365 31,075
kW-mo/yr
Natural Gas $197,295 18,152
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $100,769 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,859

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1131: Repair faulty insulation in furnaces, boilers, etc $493 $388 - - $493
-
MMBtu
02 2.1222: Install turbulators $4,953 $7,500 - - $4,953
-
MMBtu
03 2.2442: Preheat combustion air with waste heat $27,623 $20,280 - - $27,623
-
MMBtu
04 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $13,947 $350 $11,339
118,113
kWh
$2,608
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,376 $1,782 $1,354
24,486
kWh
$1,022
-
kW-mo/yr
-
06 2.7135: Install occupancy sensors $1,758 $524 $1,758
18,319
kWh
- -
07 2.7124: Make a practice of turning off lights when not needed $811 $895 $811
8,452
kWh
- -
08 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $19,232 $26,795 $16,912
176,165
kWh
$2,320
-
kW-mo/yr
-
09 2.4151: Develop a repair/replace policy $29,576 $10,400 $29,576
268,874
kWh
- -
TOTAL RECOMMENDED $100,769 $68,914 $61,750
614,409
kWh
$5,950
-
kW-mo/yr
$33,069
-
MMBtu
TOTAL IMPLEMENTED $36,859 $30,210 $30,416
327,216
kWh
$5,950
-
kW-mo/yr
$493
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs