Assessment Year | 2010 |
---|---|
Principal Product | xenograft and allograft products |
NAICS | 339113: Surgical Appliance and Supplies Manufacturing |
SIC | 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
133,072
ft2
|
Annual Production | 465,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,440,093 | 14,966,519 |
kWh
|
$0.096 |
Electricity Demand | $208,365 | 31,075 |
kW-mo/yr
|
$6.71 |
Natural Gas | $197,295 | 18,152 |
MMBtu
|
$10.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $100,769 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,859 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $493 | $388 | - | - |
$493
-
MMBtu
|
|
02 | 2.1222: Install turbulators | $4,953 | $7,500 | - | - |
$4,953
-
MMBtu
|
|
03 | 2.2442: Preheat combustion air with waste heat | $27,623 | $20,280 | - | - |
$27,623
-
MMBtu
|
|
04 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $13,947 | $350 |
$11,339
118,113
kWh
|
$2,608
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,376 | $1,782 |
$1,354
24,486
kWh
|
$1,022
-
kW-mo/yr
|
- | |
06 | 2.7135: Install occupancy sensors | $1,758 | $524 |
$1,758
18,319
kWh
|
- | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $811 | $895 |
$811
8,452
kWh
|
- | - | |
08 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $19,232 | $26,795 |
$16,912
176,165
kWh
|
$2,320
-
kW-mo/yr
|
- | |
09 | 2.4151: Develop a repair/replace policy | $29,576 | $10,400 |
$29,576
268,874
kWh
|
- | - | |
TOTAL RECOMMENDED | $100,769 | $68,914 |
$61,750
614,409
kWh
|
$5,950
-
kW-mo/yr
|
$33,069
-
MMBtu
|
||
TOTAL IMPLEMENTED | $36,859 | $30,210 |
$30,416
327,216
kWh
|
$5,950
-
kW-mo/yr
|
$493
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs