Assessment Year | 2010 |
---|---|
Principal Product | Animal Feed |
NAICS | 311119: Other Animal Food Manufacturing |
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $10 M to 50M |
# of Employees | 25 |
Plant Area |
30,000
ft2
|
Annual Production | 64,800
ton
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $122,187 | 1,589,280 |
kWh
|
$0.077 |
Electricity Demand | $6,823 | 5,890 |
kW-mo/yr
|
$1.16 |
Electricity Fees | $53,534 | - |
|
- |
Natural Gas | $69,292 | 6,860 |
MMBtu
|
$10.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $76,873 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,419 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $1,771 | $2,321 | - | - |
$1,771
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,098 | $314 |
$1,098
9,546
kWh
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $5,138 | $8,558 |
$5,138
43,975
kWh
|
- | - | |
04 | 2.2128: Use steam condensate for hot water supply (non-potable) | $21,987 | $10,000 | - | - |
$21,987
-
MMBtu
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,205 | - |
$1,205
10,474
kWh
|
- | - | |
06 | 2.4151: Develop a repair/replace policy | $621 | - |
$621
5,168
kWh
|
- | - | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $11,610 | - | - |
$11,610
-
kW-mo/yr
|
- | |
08 | 2.7243: Improve air circulation with destratification fans / other methods | $7,722 | $6,350 |
$7,722
67,146
kWh
|
- | - | |
09 | 2.2441: Preheat boiler makeup water with waste process heat | $23,836 | $4,000 | - | - |
$23,836
-
MMBtu
|
|
10 | 2.4156: Establish a preventative maintenance program | $1,885 | $816 |
$1,885
25,480
kWh
|
- | - | |
TOTAL RECOMMENDED | $76,873 | $32,359 |
$17,669
161,789
kWh
|
$11,610
-
kW-mo/yr
|
$47,594
-
MMBtu
|
||
TOTAL IMPLEMENTED | $16,419 | $1,130 |
$4,809
50,668
kWh
|
$11,610
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs