ITAC Assessment: UF0431
ITAC logo
ITAC Assessment: UF0431
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Peantut Butter, extracts
NAICS 311911: Roasted Nuts and Peanut Butter Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 140
Plant Area 23,000
ft2
Annual Production 82,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $435,145 6,655,006
kWh
Natural Gas $286,948 36,497
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,533 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Solid Waste (non-haz) Savings
01 2.7124: Make a practice of turning off lights when not needed $1,250 - $1,250
19,121
kWh
-
02 2.7145: Install skylights $1,303 $4,408 $1,303
19,918
kWh
-
03 2.4133: Use most efficient type of electric motors $13,351 $39,918 $13,351
204,134
kWh
-
04 2.6212: Turn off equipment during breaks, reduce operating time $6,300 - $6,300
96,334
kWh
-
05 2.7243: Improve air circulation with destratification fans / other methods $5,063 $1,050 $5,063
77,414
kWh
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,297 $449 $1,297
19,827
kWh
-
07 2.4231: Reduce the pressure of compressed air to the minimum required $808 - $808
12,355
kWh
-
08 2.4224: Upgrade controls on compressors $1,346 - $1,346
20,584
kWh
-
09 3.5212: Regrind, reuse, or sell scrap plastic parts $1,815 - - $1,815
-
lb
TOTAL RECOMMENDED $32,533 $45,825 $30,718
469,687
kWh
$1,815
-
lb
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs