Assessment Year | 2009 |
---|---|
Principal Product | ceiling tiles |
NAICS | 321219: Reconstituted Wood Product Manufacturing |
SIC | 2493: Reconstituted Wood Products |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
1,132,560
ft2
|
Annual Production | 150,000
thousand feet
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,564,459 | 34,327,218 |
kWh
|
$0.075 |
Natural Gas | $141,314 | 70,657 |
MMBtu
|
$2.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $252,634 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $228,223 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,286 | - |
$9,286
124,306
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,129 | $456 |
$2,129
28,505
kWh
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $61,944 | $21,313 |
$61,943
829,222
kWh
|
$1
-
kW-mo/yr
|
- | - | |
04 | 2.7124: Make a practice of turning off lights when not needed | $6,908 | $1,600 |
$6,908
92,481
kWh
|
- | - | - | |
05 | 2.7243: Improve air circulation with destratification fans / other methods | $14,600 | $12,400 |
$14,600
-
kWh
|
- | - | - | |
06 | 2.4151: Develop a repair/replace policy | $1,195 | - |
$1,195
13,917
kWh
|
- | - | - | |
07 | 2.4156: Establish a preventative maintenance program | $41,811 | $2,400 |
$41,810
559,713
kWh
|
$1
-
kW-mo/yr
|
- | - | |
08 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $2,702 | $1,800 | - | - |
$2,702
-
MMBtu
|
- | |
09 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $52,516 | $31,860 | - | - |
$52,516
-
MMBtu
|
- | |
10 | 2.4133: Use most efficient type of electric motors | $59,018 | $139,322 |
$59,017
790,056
kWh
|
$1
-
kW-mo/yr
|
- | - | |
11 | 3.5316: Contract a wood pallet recycling company | $525 | - | - | - | - | $525 | |
TOTAL RECOMMENDED | $252,634 | $211,151 |
$196,888
2,438,200
kWh
|
$3
-
kW-mo/yr
|
$55,218
-
MMBtu
|
$525 | ||
TOTAL IMPLEMENTED | $228,223 | $198,751 |
$173,002
2,313,894
kWh
|
$3
-
kW-mo/yr
|
$55,218
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs