Assessment Year | 2008 |
---|---|
Principal Product | Prestressed Concrete Strand |
NAICS | 331222: Steel Wire Drawing |
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $50 M to 100M |
# of Employees | 63 |
Plant Area |
116,000
ft2
|
Annual Production | 62,000
ton
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,743,998 | 22,464,000 |
kWh
|
$0.078 |
Natural Gas | $133,156 | 149,730 |
MMBtu
|
$0.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $217,491 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,714 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $32,847 | $36,441 |
$32,847
434,066
kWh
|
- | - | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $2,012 | - |
$2,012
28,739
kWh
|
- | - | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $10,710 | - |
$10,710
153,007
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,992 | - |
$8,992
11,530
kWh
|
- | - | |
05 | 2.4225: Install common header on compressors | $14,617 | - |
$14,617
188,101
kWh
|
- | - | |
06 | 2.4225: Install common header on compressors | $12,647 | $900 |
$12,647
180,677
kWh
|
- | - | |
07 | 2.4133: Use most efficient type of electric motors | $19,601 | $64,339 |
$19,601
251,159
kWh
|
- | - | |
08 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $3,201 | $1,200 | - |
$3,201
-
MMBtu
|
- | |
09 | 2.7243: Improve air circulation with destratification fans / other methods | $65,568 | $31,410 |
$65,568
773,149
kWh
|
- | - | |
10 | 3.4116: Meter recycled water (to reduce sewer charges) | $45,096 | $15,000 | - | - |
$45,096
-
Tgal
|
|
11 | 3.4116: Meter recycled water (to reduce sewer charges) | $2,200 | $4,158 | - | - |
$2,200
-
Tgal
|
|
TOTAL RECOMMENDED | $217,491 | $153,448 |
$166,994
2,020,428
kWh
|
$3,201
-
MMBtu
|
$47,296
-
Tgal
|
||
TOTAL IMPLEMENTED | $21,714 | - |
$21,714
193,276
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs