ITAC Assessment: UF0399
ITAC logo
ITAC Assessment: UF0399
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Filters
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 105,000
ft2
Annual Production 40,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $632,720 14,466,032
kWh
Electricity Demand $245,030 30,036
kW-mo/yr
Natural Gas $645,321 54,747
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $165,771 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $90,348

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
01 2.7243: Improve air circulation with destratification fans / other methods $3,373 $24,800 $3,373
73,325
kWh
- - - -
02 2.2531: Re-size charging openings or add movable cover or door $349 $1,376 $349
7,596
kWh
- - - -
03 2.4221: Install compressor air intakes in coolest locations $3,878 $437 $3,878
84,310
kWh
- - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $8,852 - $8,852
140,514
kWh
- - - -
05 2.2515: Use optimum thickness insulation $1,157 $188 - - $1,157
-
MMBtu
- -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $939 - $939
9,353
kWh
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $20,311 $44,692 $14,906
324,044
kWh
$5,405
-
kW-mo/yr
- - -
08 2.2414: Use waste heat from hot flue gases to preheat $47,277 $35,000 - - $47,277
-
MMBtu
- -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $2,017 $1,719 $1,929
7,556
kWh
$88
-
kW-mo/yr
- - -
10 2.7135: Install occupancy sensors $1,761 $404 $1,761
38,284
kWh
- - - -
11 3.5318: Recycle fluorescent lamps $1,005 $3,486 - - - $1,005 -
12 4.632: Change operating conditions $74,852 $731 - - - - $74,852
TOTAL RECOMMENDED $165,771 $112,833 $35,987
684,982
kWh
$5,493
-
kW-mo/yr
$48,434
-
MMBtu
$1,005 $74,852
TOTAL IMPLEMENTED $90,348 $5,058 $14,491
263,108
kWh
- - $1,005 $74,852
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs