| Assessment Year | 2007 |
|---|---|
| Principal Product | d'Limonene |
| NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
| SIC | 2840: |
| Sales Range | $10 M to 50M |
| # of Employees | 39 |
| Plant Area |
44,000
ft2
|
| Annual Production | 20,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $107,091 | 1,461,000 |
kWh
|
$0.073 |
| Electricity Demand | $25,936 | 3,105 |
kW-mo/yr
|
$8.35 |
| Electricity Fees | $17,374 | - |
|
- |
| Other Energy | $186,034 | 10,682 |
MMBtu
|
$17.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $100,444 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,162 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,223 | $4,805 |
$1,923
26,238
kWh
|
$300
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7135: Install occupancy sensors | $364 | $1,126 |
$364
4,966
kWh
|
- | - | - | - | |
| 03 | 2.6231: Utilize controls to operate equipment only when needed | $8,125 | $6,679 |
$8,125
89,183
kWh
|
- | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,101 | $642 |
$2,101
23,065
kWh
|
- | - | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $282 | $609 |
$231
3,147
kWh
|
$51
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $347 | - |
$347
2,222
kWh
|
- | - | - | - | |
| 07 | 2.2136: Install / repair insulation on steam lines | $731 | $810 | - | - |
$731
-
gal
|
- | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,401 | - |
$1,401
15,376
kWh
|
- | - | - | - | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,300 | $477 |
$3,300
36,228
kWh
|
- | - | - | - | |
| 10 | 2.1221: Replace obsolete burners with more efficient ones | $72,041 | $30,000 | - | - | - | - | $72,041 | |
| 11 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $2,041 | $4,160 |
$2,041
27,844
kWh
|
- | - | - | - | |
| 12 | 4.321: Optimize production lot sizes and inventories | $7,488 | $970 | - | - | - | $7,488 | - | |
| TOTAL RECOMMENDED | $100,444 | $50,278 |
$19,833
228,269
kWh
|
$351
-
kW-mo/yr
|
$731
-
gal
|
$7,488 | $72,041 | ||
| TOTAL IMPLEMENTED | $8,162 | $2,538 |
$7,380
80,038
kWh
|
$51
-
kW-mo/yr
|
$731
-
gal
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs