ITAC Assessment: UF0396
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product d'Limonene
NAICS 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing
SIC 2840:
Sales Range $10
M
to 50
M
# of Employees 39
Plant Area 44,000
ft2
Annual Production 20,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $107,091 1,461,000
kWh
Electricity Demand $25,936 3,105
kW-mo/yr
Electricity Fees $17,374 -
Other Energy $186,034 10,682
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $100,444 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,162

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,223 $4,805 $1,923
26,238
kWh
$300
-
kW-mo/yr
- - -
02 2.7135: Install occupancy sensors $364 $1,126 $364
4,966
kWh
- - - -
03 2.6231: Utilize controls to operate equipment only when needed $8,125 $6,679 $8,125
89,183
kWh
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,101 $642 $2,101
23,065
kWh
- - - -
05 2.4133: Use most efficient type of electric motors $282 $609 $231
3,147
kWh
$51
-
kW-mo/yr
- - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $347 - $347
2,222
kWh
- - - -
07 2.2136: Install / repair insulation on steam lines $731 $810 - - $731
-
gal
- -
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,401 - $1,401
15,376
kWh
- - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,300 $477 $3,300
36,228
kWh
- - - -
10 2.1221: Replace obsolete burners with more efficient ones $72,041 $30,000 - - - - $72,041
11 2.7491: Insulate glazing, walls, ceilings, and roofs $2,041 $4,160 $2,041
27,844
kWh
- - - -
12 4.321: Optimize production lot sizes and inventories $7,488 $970 - - - $7,488 -
TOTAL RECOMMENDED $100,444 $50,278 $19,833
228,269
kWh
$351
-
kW-mo/yr
$731
-
gal
$7,488 $72,041
TOTAL IMPLEMENTED $8,162 $2,538 $7,380
80,038
kWh
$51
-
kW-mo/yr
$731
-
gal
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs