| Assessment Year | 2007 | 
|---|---|
| Principal Product | Bottle Water | 
| NAICS | 312112: Bottled Water Manufacturing | 
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters | 
| Sales Range | $10 Mto 50 M | 
| # of Employees | 200 | 
| Plant Area | 310,000 
ft2
 | 
| Annual Production | 60,000 
Tgal
 | 
| Production Hrs. Annual | 8,760 
hrs
 | 
| Location (State) | Florida | 
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,887,557 | 24,650,102 | 
kWh
 | $0.077 | 
| Electricity Demand | $288,696 | 2,814 | 
kW-mo/yr
 | $102.59 | 
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $358,882 | See individual recommendations below*Non-energy impacts included in savings. | ||
| IMPLEMENTED SAVINGS* | $351,196 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | Increase in Production Savings | 
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,451 | $4,491 | $8,237 107,538
                                 
kWh
 | $1,214 -
                                 
kW-mo/yr
 | - | - | |
| 02 | 2.7135: Install occupancy sensors | $3,897 | $345 | $3,897 50,785
                                 
kWh
 | - | - | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $2,587 | $50 | $2,292 29,927
                                 
kWh
 | $295 -
                                 
kW-mo/yr
 | - | - | |
| 04 | 2.7141: Lower light fixtures in high ceiling areas | $1,469 | $133 | $1,275 16,644
                                 
kWh
 | $194 -
                                 
kW-mo/yr
 | - | - | |
| 05 | 2.7124: Make a practice of turning off lights when not needed | $2,409 | $30 | $2,409 31,450
                                 
kWh
 | - | - | - | |
| 06 | 2.7145: Install skylights | $19,110 | $35,054 | $12,450 162,526
                                 
kWh
 | $6,660 -
                                 
kW-mo/yr
 | - | - | |
| 07 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $3,509 | $9,776 | $3,509 45,804
                                 
kWh
 | - | - | - | |
| 08 | 2.6218: Turn off equipment when not in use | $200 | - | $49 634
                                 
kWh
 | - | $151 | - | |
| 09 | 2.7261: Install timers and/or thermostats | $2,508 | $752 | $2,508 28,407
                                 
kWh
 | - | - | - | |
| 10 | 2.5121: Redesign flow to minimize mass transfer length | $77,607 | $31,201 | $70,477 826,008
                                 
kWh
 | - | - | $7,130 | |
| 11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,271 | - | $2,210 25,028
                                 
kWh
 | - | $36 | $25 | |
| 12 | 2.4133: Use most efficient type of electric motors | $53,219 | $20,339 | $46,249 603,772
                                 
kWh
 | $6,970 -
                                 
kW-mo/yr
 | - | - | |
| 13 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $180,645 | $263,004 | $151,393 1,976,411
                                 
kWh
 | $29,252 -
                                 
kW-mo/yr
 | - | - | |
| TOTAL RECOMMENDED | $358,882 | $365,175 | $306,955 3,904,934
                                 
kWh
 | $44,585 -
                                 
kW-mo/yr
 | $187 | $7,155 | ||
| TOTAL IMPLEMENTED | $351,196 | $354,514 | $299,614 3,813,445
                                 
kWh
 | $44,391 -
                                 
kW-mo/yr
 | $36 | $7,155 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs
             
             
             
            