Assessment Year | 2007 |
---|---|
Principal Product | Bottle Water |
NAICS | 312112: Bottled Water Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
310,000
ft2
|
Annual Production | 60,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,887,557 | 24,650,102 |
kWh
|
$0.077 |
Electricity Demand | $288,696 | 2,814 |
kW-mo/yr
|
$102.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $358,882 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $351,196 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,451 | $4,491 |
$8,237
107,538
kWh
|
$1,214
-
kW-mo/yr
|
- | - | |
02 | 2.7135: Install occupancy sensors | $3,897 | $345 |
$3,897
50,785
kWh
|
- | - | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $2,587 | $50 |
$2,292
29,927
kWh
|
$295
-
kW-mo/yr
|
- | - | |
04 | 2.7141: Lower light fixtures in high ceiling areas | $1,469 | $133 |
$1,275
16,644
kWh
|
$194
-
kW-mo/yr
|
- | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $2,409 | $30 |
$2,409
31,450
kWh
|
- | - | - | |
06 | 2.7145: Install skylights | $19,110 | $35,054 |
$12,450
162,526
kWh
|
$6,660
-
kW-mo/yr
|
- | - | |
07 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $3,509 | $9,776 |
$3,509
45,804
kWh
|
- | - | - | |
08 | 2.6218: Turn off equipment when not in use | $200 | - |
$49
634
kWh
|
- | $151 | - | |
09 | 2.7261: Install timers and/or thermostats | $2,508 | $752 |
$2,508
28,407
kWh
|
- | - | - | |
10 | 2.5121: Redesign flow to minimize mass transfer length | $77,607 | $31,201 |
$70,477
826,008
kWh
|
- | - | $7,130 | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,271 | - |
$2,210
25,028
kWh
|
- | $36 | $25 | |
12 | 2.4133: Use most efficient type of electric motors | $53,219 | $20,339 |
$46,249
603,772
kWh
|
$6,970
-
kW-mo/yr
|
- | - | |
13 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $180,645 | $263,004 |
$151,393
1,976,411
kWh
|
$29,252
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $358,882 | $365,175 |
$306,955
3,904,934
kWh
|
$44,585
-
kW-mo/yr
|
$187 | $7,155 | ||
TOTAL IMPLEMENTED | $351,196 | $354,514 |
$299,614
3,813,445
kWh
|
$44,391
-
kW-mo/yr
|
$36 | $7,155 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs