| Assessment Year | 2006 |
|---|---|
| Principal Product | Refurbish Aircraft components |
| NAICS | 333318: Other Commercial and Service Industry Machinery Manufacturing |
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | less than $500 k |
| # of Employees | 125 |
| Plant Area |
225
ft2
|
| Annual Production | 300
pieces
|
| Production Hrs. Annual | 6,570
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $55,255 | 1,448,114 |
kWh
|
$0.038 |
| Electricity Demand | $13,085 | 4,579 |
kW-mo/yr
|
$2.86 |
| Natural Gas | $47,432 | 28,635 |
MMBtu
|
$1.66 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $70,758 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7134: Use photocell controls | $4,721 | $2,760 |
$3,532
58,678
kWh
|
$1,189
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,902 | $900 |
$9,902
142,477
kWh
|
- | - | - | - | |
| 03 | 2.2511: Insulate bare equipment | $1,971 | $1,275 |
$1,971
32,854
kWh
|
- | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,024 | $7,567 |
$7,515
108,130
kWh
|
$509
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7131: Add area lighting switches | $515 | $2,079 |
$515
7,415
kWh
|
- | - | - | - | |
| 06 | 2.7292: Lower ceiling to reduce conditioned space | $21,646 | $1,350 |
$21,646
359,564
kWh
|
- | - | - | - | |
| 07 | 2.7135: Install occupancy sensors | $1,876 | $571 |
$1,876
31,270
kWh
|
- | - | - | - | |
| 08 | 2.7233: Use properly designed and sized hvac equipment | $5,305 | $1,000 |
$473
7,884
kWh
|
$32
-
kW-mo/yr
|
$4,800 | - | - | |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $393 | - |
$246
1,408
kWh
|
- | $56 | - | $91 | |
| 10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,973 | - |
$1,973
28,190
kWh
|
- | - | - | - | |
| 11 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,029 | $3,200 |
$1,029
14,696
kWh
|
- | - | - | - | |
| 12 | 2.2691: Shut off cooling if cold outside air will cool process | $6,821 | - |
$6,150
102,492
kWh
|
$671
-
kW-mo/yr
|
- | - | - | |
| 13 | 3.5318: Recycle fluorescent lamps | $342 | $3,237 | - | - | - | - | $342 | |
| 14 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $6,240 | $8,000 | - | - | - | $6,240 | - | |
| TOTAL RECOMMENDED | $70,758 | $31,939 |
$56,828
895,058
kWh
|
$2,401
-
kW-mo/yr
|
$4,856 | $6,240 | $433 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs