ITAC Assessment: UF0382
ITAC logo
ITAC Assessment: UF0382
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Refurbish Aircraft components
NAICS 333318: Other Commercial and Service Industry Machinery Manufacturing
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range less than $500
k
# of Employees 125
Plant Area 225
ft2
Annual Production 300
pieces
Production Hrs. Annual 6,570
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,255 1,448,114
kWh
Electricity Demand $13,085 4,579
kW-mo/yr
Natural Gas $47,432 28,635
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $70,758 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7134: Use photocell controls $4,721 $2,760 $3,532
58,678
kWh
$1,189
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,902 $900 $9,902
142,477
kWh
- - - -
03 2.2511: Insulate bare equipment $1,971 $1,275 $1,971
32,854
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $8,024 $7,567 $7,515
108,130
kWh
$509
-
kW-mo/yr
- - -
05 2.7131: Add area lighting switches $515 $2,079 $515
7,415
kWh
- - - -
06 2.7292: Lower ceiling to reduce conditioned space $21,646 $1,350 $21,646
359,564
kWh
- - - -
07 2.7135: Install occupancy sensors $1,876 $571 $1,876
31,270
kWh
- - - -
08 2.7233: Use properly designed and sized hvac equipment $5,305 $1,000 $473
7,884
kWh
$32
-
kW-mo/yr
$4,800 - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $393 - $246
1,408
kWh
- $56 - $91
10 2.4231: Reduce the pressure of compressed air to the minimum required $1,973 - $1,973
28,190
kWh
- - - -
11 2.7447: Install vinyl strip / high speed / air curtain doors $1,029 $3,200 $1,029
14,696
kWh
- - - -
12 2.2691: Shut off cooling if cold outside air will cool process $6,821 - $6,150
102,492
kWh
$671
-
kW-mo/yr
- - -
13 3.5318: Recycle fluorescent lamps $342 $3,237 - - - - $342
14 3.6193: Install equipment (eg compactor) to reduce disposal costs $6,240 $8,000 - - - $6,240 -
TOTAL RECOMMENDED $70,758 $31,939 $56,828
895,058
kWh
$2,401
-
kW-mo/yr
$4,856 $6,240 $433
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs