ITAC Assessment: UF0372
ITAC logo
ITAC Assessment: UF0372
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product saw blades
NAICS 332216: Saw Blade and Handtool Manufacturing
SIC 3425: Saw Blades and Handsaws
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 120,000
ft2
Annual Production 42,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $291,526 5,010,930
kWh
Electricity Demand $78,571 10,573
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,304,199 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,135,631

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
01 2.7141: Lower light fixtures in high ceiling areas $22,802 $2,143 $18,918
326,177
kWh
$3,884
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $8,373 $10,886 $6,962
120,035
kWh
$1,411
-
kW-mo/yr
- -
03 2.7141: Lower light fixtures in high ceiling areas $2,383 - $2,383
41,088
kWh
- - -
04 2.7135: Install occupancy sensors $3,070 $1,427 $3,070
52,925
kWh
- - -
05 2.7111: Reduce illumination to minimum necessary levels $10,158 $28,067 $10,158
175,136
kWh
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $55,681 $32,374 $46,230
797,059
kWh
$9,451
-
kW-mo/yr
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $16,223 $16,223 $16,223
279,702
kWh
- - -
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $15,724 $39,583 $10,316
177,873
kWh
$5,408
-
kW-mo/yr
- -
09 2.7232: Replace existing hvac unit with high efficiency model $43,072 $138,308 $10,857
1,872,000
kWh
$535
-
kW-mo/yr
$31,680 -
10 2.7491: Insulate glazing, walls, ceilings, and roofs $26,386 $121,152 $26,386
356,571
kWh
- - -
11 2.7447: Install vinyl strip / high speed / air curtain doors $4,054 $4,144 $4,054
54,787
kWh
- - -
12 2.4133: Use most efficient type of electric motors $6,916 $15,057 $5,233
90,228
kWh
$1,683
-
kW-mo/yr
- -
13 2.7243: Improve air circulation with destratification fans / other methods $14,477 $62,000 $14,477
249,600
kWh
- - -
14 4.111: Add equipment/ operators to reduce production bottleneck $1,074,880 $989 - - - $1,074,880
TOTAL RECOMMENDED $1,304,199 $472,353 $175,267
4,593,181
kWh
$22,372
-
kW-mo/yr
$31,680 $1,074,880
TOTAL IMPLEMENTED $1,135,631 $49,442 $53,773
912,017
kWh
$6,978
-
kW-mo/yr
- $1,074,880
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs