ITAC Assessment: UF0370
ITAC logo
ITAC Assessment: UF0370
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product professional beauty products
NAICS 325620: Toilet Preparation Manufacturing
SIC 2844: Perfumes, Cosmetics, and Other Toilet Preparations
Sales Range $100
M
to 500
M
# of Employees 200
Plant Area 350,000
ft2
Annual Production 55,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $483,461 8,799,096
kWh
Electricity Demand $151,310 29,903
kW-mo/yr
Natural Gas $197,148 19,490
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $156,965 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $75,835

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.7141: Lower light fixtures in high ceiling areas $2,736 $1,212 $2,021
50,519
kWh
$715
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $20,004 $1,286 $6,456
161,404
kWh
$2,287
-
kW-mo/yr
- - - $11,260
03 2.4235: Remove or close off unneeded compressed air lines $20,435 $56,000 $20,435
346,350
kWh
- - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,994 $731 $10,994
186,335
kWh
- - - - -
05 2.2628: Utilize a less expensive cooling method $43,146 $1,190 $16,869
421,732
kWh
$26,276
-
kW-mo/yr
- - - -
06 2.7124: Make a practice of turning off lights when not needed $2,525 - $1,747
43,680
kWh
$778
-
kW-mo/yr
- - - -
07 2.2511: Insulate bare equipment $4,053 $1,317 - - $4,053
-
MMBtu
- - -
08 2.7135: Install occupancy sensors $926 $959 $926
23,139
kWh
- - - - -
09 2.2622: Replace existing chiller with high efficiency model $47,299 $130,000 $30,010
750,250
kWh
$17,289
-
kW-mo/yr
- - - -
10 2.4221: Install compressor air intakes in coolest locations $313 $760 $313
5,312
kWh
- - - - -
11 3.5316: Contract a wood pallet recycling company $1,313 - - - - - $1,313 -
12 4.424: Improve space comfort conditioning $3,223 $12,400 $1,807
45,178
kWh
$704
-
kW-mo/yr
- $712 - -
TOTAL RECOMMENDED $156,965 $205,855 $91,578
2,033,899
kWh
$48,049
-
kW-mo/yr
$4,053
-
MMBtu
$712 $1,313 $11,260
TOTAL IMPLEMENTED $75,835 $188,529 $52,465
1,147,119
kWh
$18,004
-
kW-mo/yr
$4,053
-
MMBtu
- $1,313 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs