| Assessment Year | 2005 |
|---|---|
| Principal Product | professional beauty products |
| NAICS | 325620: Toilet Preparation Manufacturing |
| SIC | 2844: Perfumes, Cosmetics, and Other Toilet Preparations |
| Sales Range | $100 M to 500M |
| # of Employees | 200 |
| Plant Area |
350,000
ft2
|
| Annual Production | 55,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $483,461 | 8,799,096 |
kWh
|
$0.055 |
| Electricity Demand | $151,310 | 29,903 |
kW-mo/yr
|
$5.06 |
| Natural Gas | $197,148 | 19,490 |
MMBtu
|
$10.12 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $156,965 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $75,835 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7141: Lower light fixtures in high ceiling areas | $2,736 | $1,212 |
$2,021
50,519
kWh
|
$715
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,004 | $1,286 |
$6,456
161,404
kWh
|
$2,287
-
kW-mo/yr
|
- | - | - | $11,260 | |
| 03 | 2.4235: Remove or close off unneeded compressed air lines | $20,435 | $56,000 |
$20,435
346,350
kWh
|
- | - | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,994 | $731 |
$10,994
186,335
kWh
|
- | - | - | - | - | |
| 05 | 2.2628: Utilize a less expensive cooling method | $43,146 | $1,190 |
$16,869
421,732
kWh
|
$26,276
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $2,525 | - |
$1,747
43,680
kWh
|
$778
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.2511: Insulate bare equipment | $4,053 | $1,317 | - | - |
$4,053
-
MMBtu
|
- | - | - | |
| 08 | 2.7135: Install occupancy sensors | $926 | $959 |
$926
23,139
kWh
|
- | - | - | - | - | |
| 09 | 2.2622: Replace existing chiller with high efficiency model | $47,299 | $130,000 |
$30,010
750,250
kWh
|
$17,289
-
kW-mo/yr
|
- | - | - | - | |
| 10 | 2.4221: Install compressor air intakes in coolest locations | $313 | $760 |
$313
5,312
kWh
|
- | - | - | - | - | |
| 11 | 3.5316: Contract a wood pallet recycling company | $1,313 | - | - | - | - | - | $1,313 | - | |
| 12 | 4.424: Improve space comfort conditioning | $3,223 | $12,400 |
$1,807
45,178
kWh
|
$704
-
kW-mo/yr
|
- | $712 | - | - | |
| TOTAL RECOMMENDED | $156,965 | $205,855 |
$91,578
2,033,899
kWh
|
$48,049
-
kW-mo/yr
|
$4,053
-
MMBtu
|
$712 | $1,313 | $11,260 | ||
| TOTAL IMPLEMENTED | $75,835 | $188,529 |
$52,465
1,147,119
kWh
|
$18,004
-
kW-mo/yr
|
$4,053
-
MMBtu
|
- | $1,313 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs