ITAC Assessment: UF0367
ITAC logo
ITAC Assessment: UF0367
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Ice
NAICS 312113: Ice Manufacturing
SIC 2097: Manufactured Ice
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area 21,000
ft2
Annual Production 4,000,000
pieces
Production Hrs. Annual 4,380
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $124,151 1,956,240
kWh
Electricity Demand $25,181 344
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,597 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,773

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7124: Make a practice of turning off lights when not needed $124 - $124
6,546
kWh
02 2.6218: Turn off equipment when not in use $200 - $200
10,512
kWh
03 3.1181: Eliminate a by-product $4,483 $870 $4,483
23,593
kWh
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,578 - $2,578
35,216
kWh
05 2.4133: Use most efficient type of electric motors $3,614 $3,948 $3,614
58,631
kWh
06 3.1181: Eliminate a by-product $426 $300 $426
22,425
kWh
07 2.2511: Insulate bare equipment $1,974 $700 $1,974
31,335
kWh
08 2.6231: Utilize controls to operate equipment only when needed $7,198 $23,500 $7,198
98,132
kWh
TOTAL RECOMMENDED $20,597 $29,318 $20,597
286,390
kWh
TOTAL IMPLEMENTED $12,773 $5,518 $12,773
155,321
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs