Assessment Year | 1996 |
---|---|
Principal Product | After Market Cabs & Roll Over Bars |
NAICS |
n/a
|
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $5 M to 10M |
# of Employees | 113 |
Plant Area |
88,076
ft2
|
Annual Production | 30,000
pieces
|
Production Hrs. Annual | 6,500
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $30,635 | 1,549,531 |
kWh
|
$0.020 |
Electricity Demand | $36,033 | 7,716 |
kW-mo/yr
|
$4.67 |
Electricity Fees | $1,209 | - |
|
- |
Natural Gas | $33,317 | 13,194 |
MMBtu
|
$2.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $75,903 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,131 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Primary Raw Material Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,316 | $11,936 |
$1,935
98,183
kWh
|
$1,381
-
kW-mo/yr
|
- | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $949 | $2,852 |
$417
21,102
kWh
|
$532
-
kW-mo/yr
|
- | - | - | |
03 | 2.4322: Use or replace with energy efficient substitutes | $1,415 | $3,500 |
$460
23,447
kWh
|
$955
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,866 | $240 |
$1,866
94,959
kWh
|
- | - | - | - | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,755 | $4,750 | - | - | - | - | $1,755 | |
06 | 3.2121: Convert to electrostatic powder coating | $39,602 | $6,000 | - | - |
$2,082
-
gal
|
$37,520 | - | |
07 | 3.1192: Reduce scrap production | $27,000 | $15,600 | - | - | - | $27,000 | - | |
TOTAL RECOMMENDED | $75,903 | $44,878 |
$4,678
237,691
kWh
|
$2,868
-
kW-mo/yr
|
$2,082
-
gal
|
$64,520 | $1,755 | ||
TOTAL IMPLEMENTED | $33,131 | $30,628 |
$4,218
214,244
kWh
|
$1,913
-
kW-mo/yr
|
- | $27,000 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Primary Raw Material Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs