ITAC Assessment: UF0353
ITAC logo
ITAC Assessment: UF0353
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Packing and Processing Mixed Nuts
NAICS 311911: Roasted Nuts and Peanut Butter Manufacturing
SIC 2068: Salted and Roasted Nuts and Seeds
Sales Range $10
M
to 50
M
# of Employees 41
Plant Area 90,000
ft2
Annual Production 12,000,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $49,451 969,936
kWh
Electricity Demand $24,993 4,168
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,383 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,984

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.4133: Use most efficient type of electric motors $2,666 $2,499 $1,802
35,341
kWh
$864
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,503 $546 $1,503
29,466
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,132 $2,140 $844
16,547
kWh
$288
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $399 - $399
7,830
kWh
- -
05 3.5313: Increase amount of waste recovered for resale $17,635 - - - $17,635
-
lb
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,048 $8,000 - - $3,048
-
lb
TOTAL RECOMMENDED $26,383 $13,185 $4,548
89,184
kWh
$1,152
-
kW-mo/yr
$20,683
-
lb
TOTAL IMPLEMENTED $25,984 $13,185 $4,149
81,354
kWh
$1,152
-
kW-mo/yr
$20,683
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs