Assessment Year | 2003 |
---|---|
Principal Product | Flush Doors |
NAICS | 321911: Wood Window and Door Manufacturing |
SIC | 2431: Millwork |
Sales Range | n/a |
# of Employees | 135 |
Plant Area |
65,000
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 5,590
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $193,125 | 2,560,320 |
kWh
|
$0.075 |
Electricity Demand | $55,875 | 7,399 |
kW-mo/yr
|
$7.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,253 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,978 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $6,357 | $18,567 |
$4,424
83,467
kWh
|
$1,933
-
kW-mo/yr
|
- | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,423 | - |
$2,157
28,759
kWh
|
- | - | - | $1,266 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,837 | $11,405 |
$4,507
82,099
kWh
|
$1,330
-
kW-mo/yr
|
- | - | - | |
04 | 2.7131: Add area lighting switches | $924 | $1,649 |
$924
12,316
kWh
|
- | - | - | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $7,190 | $32,481 |
$7,190
95,869
kWh
|
- | - | - | - | |
06 | 2.7313: Recycle air for heating, ventilation and air conditioning | $14,275 | $55,800 |
$10,932
206,271
kWh
|
$3,343
-
kW-mo/yr
|
- | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $907 | - |
$907
12,098
kWh
|
- | - | - | - | |
08 | 4.431: Train operators for maximum operating efficiency | $7,000 | $3,000 | - | - | - | $7,000 | - | |
09 | 4.423: Move product using mechanical means | $2,340 | $2,372 | - | - | $2,340 | - | - | |
TOTAL RECOMMENDED | $48,253 | $125,274 |
$31,041
520,879
kWh
|
$6,606
-
kW-mo/yr
|
$2,340 | $7,000 | $1,266 | ||
TOTAL IMPLEMENTED | $33,978 | $69,474 |
$20,109
314,608
kWh
|
$3,263
-
kW-mo/yr
|
$2,340 | $7,000 | $1,266 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs