ITAC Assessment: UF0308
ITAC logo
ITAC Assessment: UF0308
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Aluminum and Vinyl Windows
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $5
M
to 10
M
# of Employees 120
Plant Area 74,000
ft2
Annual Production 75,000
pieces
Production Hrs. Annual 5,304
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,093 1,342,968
kWh
Electricity Demand $19,407 4,322
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,675 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,465 $10,121 n/a $2,009
52,866
kWh
$456
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,612 $500 n/a $6,630
125,100
kWh
- $(-18.0) -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,366 - n/a $1,366
25,775
kWh
- - -
04 2.7447: Install vinyl strip / high speed / air curtain doors $5,184 $1,033 n/a $5,184
97,815
kWh
- - -
05 2.2511: Insulate bare equipment $4,591 $291 n/a $3,105
81,704
kWh
- - $1,486
06 2.7491: Insulate glazing, walls, ceilings, and roofs $5,687 $19,500 n/a $5,687
107,311
kWh
- - -
07 4.448: Install automatic part storage / retreval system $4,770 $864 n/a - - $4,770 -
TOTAL RECOMMENDED $30,675 $32,309 $23,981
490,571
kWh
$456
-
kW-mo/yr
$4,752 $1,486
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs