Assessment Year | 2007 |
---|---|
Principal Product | Outboard motors |
NAICS | 333618: Other Engine Equipment Manufacturing |
SIC | 3519: Internal Combustion Engines, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
34,000
ft2
|
Annual Production | 220,000
units
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $305,901 | 6,797,800 |
kWh
|
$0.045 |
Electricity Demand | $66,178 | 11,160 |
kW-mo/yr
|
$5.93 |
Electricity Fees | $39,532 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,883 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $8,264 | $915 |
$7,000
155,553
kWh
|
$1,264
-
kW-mo/yr
|
|
02 | 2.7122: Disconnect ballasts | $5,169 | $2,150 |
$3,864
85,862
kWh
|
$1,305
-
kW-mo/yr
|
|
03 | 2.4322: Use or replace with energy efficient substitutes | $4,272 | $10,200 |
$3,360
59,997
kWh
|
$912
-
kW-mo/yr
|
|
04 | 2.7145: Install skylights | $5,197 | $16,736 |
$3,448
76,677
kWh
|
$1,749
-
kW-mo/yr
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,440 | $1,074 |
$1,921
34,309
kWh
|
$519
-
kW-mo/yr
|
|
06 | 2.4323: Use optimum size and capacity equipment | $1,961 | $3,010 |
$1,705
30,454
kWh
|
$256
-
kW-mo/yr
|
|
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,128 | $1,423 |
$874
15,610
kWh
|
$254
-
kW-mo/yr
|
|
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $452 | $160 |
$338
7,514
kWh
|
$114
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $28,883 | $35,668 |
$22,510
465,976
kWh
|
$6,373
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs