Assessment Year | 2002 |
---|---|
Principal Product | Electronic Control & Monitoring Systems |
NAICS |
n/a
|
SIC | 3812: Search, Detection, Navigation, Guidance, Aeronautical, and Nautical Systems and Instruments |
Sales Range | n/a |
# of Employees | 420 |
Plant Area |
165,000
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 5,304
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $307,854 | 8,101,410 |
kWh
|
$0.038 |
Electricity Demand | $126,870 | 25,476 |
kW-mo/yr
|
$4.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $185,692 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $53,122 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7144: Install spectral reflectors / delamp | $26,416 | $12,233 |
$26,416
480,296
kWh
|
- | - | - | |
02 | 2.7132: Install timers on light switches in little used areas | $5,458 | $8,116 |
$3,665
96,451
kWh
|
$1,793
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $26,706 | $107,644 |
$20,550
540,800
kWh
|
$6,156
-
kW-mo/yr
|
- | - | |
04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $36,062 | $107,250 |
$36,062
655,667
kWh
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,754 | $2,000 |
$1,754
31,892
kWh
|
- | - | - | |
06 | 2.6225: Eliminate third shift | $11,540 | - |
$11,540
209,813
kWh
|
- | - | - | |
07 | 2.8121: Apply for tax-free status for energy purchases | $39,511 | $50 | - | - | - | $39,511 | |
08 | 3.5318: Recycle fluorescent lamps | $1,147 | $1,895 | - | - | $1,147 | - | |
09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $37,098 | $15,000 | - | - | $37,098 | - | |
TOTAL RECOMMENDED | $185,692 | $254,188 |
$99,987
2,014,919
kWh
|
$7,949
-
kW-mo/yr
|
$38,245 | $39,511 | ||
TOTAL IMPLEMENTED | $53,122 | $119,877 |
$46,966
1,021,096
kWh
|
$6,156
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs