ITAC Assessment: UF0293
ITAC logo
ITAC Assessment: UF0293
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Carbonated Soft Drinks
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area 430,000
ft2
Annual Production 27,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $338,156 6,281,340
kWh
Electricity Demand $106,133 14,639
kW-mo/yr
Natural Gas $81,039 30,982
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $384,531 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings Increase in Production Savings
01 2.4133: Use most efficient type of electric motors $20,692 $12,162 n/a $17,116
316,964
kWh
$3,576
-
kW-mo/yr
- - - - - - -
02 2.6231: Utilize controls to operate equipment only when needed $24,940 $30,000 n/a $24,940
341,644
kWh
- - - - - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $34,684 $23,130 n/a $28,541
528,538
kWh
$6,143
-
kW-mo/yr
- - - - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,852 $550 n/a $4,912
66,467
kWh
- - - - $(-60.0) - - -
05 2.7221: Lower temperature during the winter season and vice-versa $2,029 $3,500 n/a - - $2,029
-
MMBtu
- - - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,444 $4,753 n/a $1,045
19,347
kWh
$399
-
kW-mo/yr
- - - - - - -
07 2.1211: Move boiler to more efficient location $1,449 - n/a - - $1,449
-
MMBtu
- - - - - -
08 2.7121: Utilize daylight whenever possible in lieu of artificial light $11,069 $50,413 n/a $7,351
136,143
kWh
$4,218
-
kW-mo/yr
- - - $(-500.0) - - -
09 2.7135: Install occupancy sensors $3,373 $828 n/a $3,373
46,213
kWh
- - - - - - - -
10 3.5311: Recover and reuse waste material $83,104 $400,000 n/a - - - - - - $83,104 - -
11 3.6193: Install equipment (eg compactor) to reduce disposal costs $642 $1,895 n/a - - - - - $642 - - -
12 3.4155: Meter waste water $5,209 $1,700 n/a - - - $5,209
-
Tgal
- - - - -
13 4.511: Expand operations into unused space $40,000 $4,838 n/a - - - - $40,000 - - - -
14 2.7491: Insulate glazing, walls, ceilings, and roofs $133,295 $97,500 n/a - - - - - - - - $133,295
15 4.632: Change operating conditions $4,941 $5,000 n/a - - - - - - - $4,941 -
16 4.448: Install automatic part storage / retreval system $2,808 $864 n/a - - - - - $2,808 - - -
17 4.514: Re-arrange equipment layout to reduce handling costs $10,000 $752 n/a - - - - - $10,000 - - -
TOTAL RECOMMENDED $384,531 $637,885 $87,278
1,455,316
kWh
$14,336
-
kW-mo/yr
$3,478
-
MMBtu
$5,209
-
Tgal
$40,000 $12,890 $83,104 $4,941 $133,295
TOTAL IMPLEMENTED - - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs