Assessment Year | 2001 |
---|---|
Principal Product | Mattresses |
NAICS |
n/a
|
SIC | 2515: Mattresses, Foundations, and Convertible Beds |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
152,000
ft2
|
Annual Production | 468,000
pieces
|
Production Hrs. Annual | 5,304
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $110,401 | 2,912,960 |
kWh
|
$0.038 |
Electricity Demand | $37,169 | 7,013 |
kW-mo/yr
|
$5.30 |
Natural Gas | $32,558 | 2,789 |
MMBtu
|
$11.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $191,357 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $58,542 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $11,113 | $50 | - | - | $11,113 | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,296 | $28,400 |
$16,259
345,932
kWh
|
$4,037
-
kW-mo/yr
|
- | - | |
03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $32,895 | $49,350 |
$19,305
410,754
kWh
|
$10,494
-
kW-mo/yr
|
$3,096 | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $942 | $2,000 |
$942
20,039
kWh
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,343 | $340 |
$5,379
89,647
kWh
|
- | $(-36.0) | - | |
06 | 2.4323: Use optimum size and capacity equipment | $6,986 | $9,000 |
$6,986
116,438
kWh
|
- | - | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $682 | $1,895 | - | - | $682 | - | |
08 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $78,000 | $98,800 | - | - | - | $78,000 | |
09 | 4.448: Install automatic part storage / retreval system | $35,100 | $4,494 | - | - | $35,100 | - | |
TOTAL RECOMMENDED | $191,357 | $194,329 |
$48,871
982,810
kWh
|
$14,531
-
kW-mo/yr
|
$49,955 | $78,000 | ||
TOTAL IMPLEMENTED | $58,542 | $13,884 |
$12,365
206,085
kWh
|
- | $46,177 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs