| Assessment Year | 2001 |
|---|---|
| Principal Product | Acoustical Ceiling Tiles |
| NAICS |
n/a
|
| SIC | 3296: Mineral Wool |
| Sales Range | $100 M to 500M |
| # of Employees | 300 |
| Plant Area |
1,132,560
ft2
|
| Annual Production | 150,000
thousand feet
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $914,469 | 37,784,975 |
kWh
|
$0.024 |
| Electricity Demand | $658,925 | 71,520 |
kW-mo/yr
|
$9.21 |
| Natural Gas | $2,818,245 | 667,601 |
MMBtu
|
$4.22 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $648,788 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $248,075 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $46,074 | $2,910 |
$21,543
797,888
kWh
|
$23,904
-
kW-mo/yr
|
- | - | $627 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $190,612 | $67,472 |
$148,650
5,505,539
kWh
|
$41,962
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $703 | $621 |
$703
15,614
kWh
|
- | - | - | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $56,760 | $143,877 |
$41,493
1,536,765
kWh
|
$15,267
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.3212: Optimize plant power factor | $19,545 | $36,000 | - | - | - | - | $19,545 | |
| 06 | 2.4226: Use / purchase optimum sized compressor | $26,575 | $46,800 |
$22,055
816,870
kWh
|
$4,520
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.7212: Install or upgrade insulation on hvac distribution systems | $191,133 | $282,000 | - | - |
$191,133
-
MMBtu
|
- | - | |
| 08 | 2.7226: Use computer programs to optimize hvac performance | $5,102 | $20,000 |
$5,102
188,963
kWh
|
- | - | - | - | |
| 09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $682 | $1,895 | - | - | - |
$682
-
lb
|
- | |
| 10 | 4.431: Train operators for maximum operating efficiency | $111,602 | $1,600 |
$81,504
3,018,656
kWh
|
$30,098
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $648,788 | $603,175 |
$321,050
11,880,295
kWh
|
$115,751
-
kW-mo/yr
|
$191,133
-
MMBtu
|
$682
-
lb
|
$20,172 | ||
| TOTAL IMPLEMENTED | $248,075 | $211,970 |
$190,846
7,057,918
kWh
|
$57,229
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs