Assessment Year | 2001 |
---|---|
Principal Product | Truck Mounted Sewer and Catch basin Cleaning Equipment |
NAICS |
n/a
|
SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
64,000
ft2
|
Annual Production | 370
units
|
Production Hrs. Annual | 5,928
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $173,920 | 3,051,583 |
kWh
|
$0.057 |
Electricity Demand | $35,572 | 7,593 |
kW-mo/yr
|
$4.68 |
Fuel Oil #2 | $(-2,760.0) | 84 |
MMBtu
|
$(-32.857) |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $279,832 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $213,696 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Administrative Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4225: Install common header on compressors | $4,038 | $4,300 |
$4,038
67,409
kWh
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,164 | $3,861 |
$1,591
39,859
kWh
|
$573
-
kW-mo/yr
|
- | - | - | |
03 | 2.3191: Use demand controller or load shedder | $6,334 | $30,000 |
$6,334
105,510
kWh
|
- | - | - | - | |
04 | 2.7134: Use photocell controls | $7,800 | $25,000 |
$4,985
124,560
kWh
|
$3,790
-
kW-mo/yr
|
- | $(-975.0) | - | |
05 | 4.652: Replace existing equipment with more suitable substitutes | $1,753 | $1,025 |
$1,753
43,962
kWh
|
- | - | - | - | |
06 | 2.6125: Keep equipment clean | $1,578 | $252 |
$1,578
39,566
kWh
|
- | - | - | - | |
07 | 2.3192: Use fossil fuel powered generator during peak demand periods | $36,614 | $72,000 | - | - |
$(-2,760.0)
-
MMBtu
|
$39,374 | - | |
08 | 2.8121: Apply for tax-free status for energy purchases | $11,648 | $50 | - | - | - | $11,648 | - | |
09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $15,233 | $8,000 | - | - | - | $15,233 | - | |
10 | 4.611: Begin a practice of predictive / preventative maintenance | $27,670 | $1,800 | - | - | - | $27,670 | - | |
11 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $165,000 | $42,000 | - | - | - | - | $165,000 | |
TOTAL RECOMMENDED | $279,832 | $188,288 |
$20,279
420,866
kWh
|
$4,363
-
kW-mo/yr
|
$(-2,760.0)
-
MMBtu
|
$92,950 | $165,000 | ||
TOTAL IMPLEMENTED | $213,696 | $69,102 |
$6,563
164,126
kWh
|
$3,790
-
kW-mo/yr
|
- | $38,343 | $165,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Administrative Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs