Assessment Year | 2001 |
---|---|
Principal Product | Newspaper Printing |
NAICS |
n/a
|
SIC | 2711: Newspapers: Publishing, or Publishing and Printing |
Sales Range | $10 M to 50M |
# of Employees | 290 |
Plant Area |
100,000
ft2
|
Annual Production | 60,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $177,246 | 3,855,693 |
kWh
|
$0.046 |
Electricity Demand | $58,662 | 8,091 |
kW-mo/yr
|
$7.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $240,906 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,774 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7141: Lower light fixtures in high ceiling areas | $2,310 | $7,321 |
$2,380
35,995
kWh
|
- | - | $(-70.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $674 | $737 |
$552
12,264
kWh
|
$122
-
kW-mo/yr
|
- | - | |
03 | 2.7135: Install occupancy sensors | $6,321 | $3,892 |
$6,321
140,466
kWh
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $828 | $1,200 | - |
$48
-
kW-mo/yr
|
$217 | $563 | |
05 | 2.8121: Apply for tax-free status for energy purchases | $28,774 | $50 | - | - | - | $28,774 | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,346 | $530 |
$2,452
35,031
kWh
|
- | - | $(-106.0) | |
07 | 2.2515: Use optimum thickness insulation | $1,022 | $933 |
$1,022
14,596
kWh
|
- | - | - | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $323 | $1,895 | - | - | - | $323 | |
09 | 3.5316: Contract a wood pallet recycling company | $2,400 | - | - | - | - | $2,400 | |
10 | 4.231: Purchase equipment instead of leasing | $192,931 | - | - | - | - | $192,931 | |
11 | 4.431: Train operators for maximum operating efficiency | $2,977 | $800 | - | - | - | $2,977 | |
TOTAL RECOMMENDED | $240,906 | $17,358 |
$12,727
238,352
kWh
|
$170
-
kW-mo/yr
|
$217 | $227,792 | ||
TOTAL IMPLEMENTED | $28,774 | $50 | - | - | - | $28,774 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs