Assessment Year | 2001 |
---|---|
Principal Product | Blow molded plastic parts |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
118,500
ft2
|
Annual Production | 6,240,000
pieces
|
Production Hrs. Annual | 5,760
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $216,691 | 6,566,400 |
kWh
|
$0.033 |
Electricity Demand | $108,930 | 15,048 |
kW-mo/yr
|
$7.24 |
Natural Gas | $24,342 | 2,112 |
MMBtu
|
$11.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $122,715 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $38,147 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $35,895 | $7,000 | - | - | - |
$19,320
-
lb
|
$16,575 | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,711 | $55,200 |
$14,307
433,541
kWh
|
$5,404
-
kW-mo/yr
|
- | - | - | |
03 | 2.3212: Optimize plant power factor | $17,969 | $9,000 | - |
$17,969
-
kW-mo/yr
|
- | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,246 | $15,500 |
$10,216
309,857
kWh
|
$5,030
-
kW-mo/yr
|
- | - | - | |
05 | 2.2511: Insulate bare equipment | $11,223 | $7,600 |
$7,464
226,195
kWh
|
$3,759
-
kW-mo/yr
|
- | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,414 | $33,000 |
$6,107
185,069
kWh
|
$2,307
-
kW-mo/yr
|
- | - | - | |
07 | 2.8114: Change rate schedules or other changes in utility service | $4,858 | - | - | - |
$4,858
-
MMBtu
|
- | - | |
08 | 2.2437: Recover waste heat from equipment | $4,827 | $4,000 | - | - |
$4,827
-
MMBtu
|
- | - | |
09 | 2.4322: Use or replace with energy efficient substitutes | $4,097 | $3,200 |
$2,623
79,488
kWh
|
$1,474
-
kW-mo/yr
|
- | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $475 | - |
$304
9,216
kWh
|
$171
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $122,715 | $134,500 |
$41,021
1,243,366
kWh
|
$36,114
-
kW-mo/yr
|
$9,685
-
MMBtu
|
$19,320
-
lb
|
$16,575 | ||
TOTAL IMPLEMENTED | $38,147 | $19,800 |
$10,087
305,683
kWh
|
$23,202
-
kW-mo/yr
|
$4,858
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs