Assessment Year | 2000 |
---|---|
Principal Product | Water Meters |
NAICS |
n/a
|
SIC | 3824: Totalizing Fluid Meters and Counting Devices |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
90,000
ft2
|
Annual Production | 600,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $147,178 | 2,373,095 |
kWh
|
$0.062 |
Electricity Demand | $41,686 | 7,006 |
kW-mo/yr
|
$5.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $102,533 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,382 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,865 | $2,831 |
$5,061
81,770
kWh
|
$804
-
kW-mo/yr
|
- | - | |
02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $5,242 | $12,014 |
$5,242
65,651
kWh
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $1,732 | $7,400 |
$1,204
19,343
kWh
|
$528
-
kW-mo/yr
|
- | - | |
04 | 2.8121: Apply for tax-free status for energy purchases | $10,323 | $50 | - | - | $10,323 | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,597 | $460 |
$2,645
33,118
kWh
|
- | $(-48.0) | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,740 | - |
$2,740
34,291
kWh
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $835 | $1,500 |
$835
13,482
kWh
|
- | - | - | |
08 | 2.7135: Install occupancy sensors | $481 | $834 |
$481
7,620
kWh
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $704 | $600 |
$230
3,810
kWh
|
$30
-
kW-mo/yr
|
$444 | - | |
10 | 3.4155: Meter waste water | $2,940 | $1,500 | - | - | $2,940 | - | |
11 | 4.611: Begin a practice of predictive / preventative maintenance | $1,874 | $3,721 | - | - | $1,874 | - | |
12 | 4.711: Initiate a total quality management program | $67,200 | $84,000 | - | - | - | $67,200 | |
TOTAL RECOMMENDED | $102,533 | $114,910 |
$18,438
259,085
kWh
|
$1,362
-
kW-mo/yr
|
$15,533 | $67,200 | ||
TOTAL IMPLEMENTED | $27,382 | $13,675 |
$12,361
179,952
kWh
|
$1,362
-
kW-mo/yr
|
$13,659 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs