ITAC Assessment: UF0256
ITAC logo
ITAC Assessment: UF0256
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Business Forms and Laser Cut Sheets
NAICS
n/a
SIC 2761: Manifold Business Forms
Sales Range $10
M
to 50
M
# of Employees 92
Plant Area 30,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $105,079 2,390,680
kWh
Electricity Demand $35,356 6,671
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $234,601 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
01 2.7261: Install timers and/or thermostats $5,306 $650 n/a $5,306
120,457
kWh
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,388 $1,261 n/a $4,682
106,389
kWh
$706
-
kW-mo/yr
- - -
03 2.8121: Apply for tax-free status for energy purchases $4,915 $50 n/a - - - - $4,915
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $231 $300 n/a $231
1,758
kWh
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,166 $320 n/a $3,166
29,894
kWh
- - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $593 - n/a $593
10,258
kWh
- - - -
07 4.652: Replace existing equipment with more suitable substitutes $134 $200 n/a $51
1,172
kWh
$8
-
kW-mo/yr
- $75 -
08 2.7226: Use computer programs to optimize hvac performance $7,547 $20,000 n/a $7,547
148,886
kWh
- - - -
09 2.4133: Use most efficient type of electric motors $6,944 $25,000 n/a $5,513
125,440
kWh
$1,431
-
kW-mo/yr
- - -
10 3.4155: Meter waste water $377 $1,500 n/a - - $377
-
Tgal
- -
11 4.111: Add equipment/ operators to reduce production bottleneck $50,000 $60,000 n/a - - - - $50,000
12 4.111: Add equipment/ operators to reduce production bottleneck $150,000 $100,000 n/a - - - - $150,000
TOTAL RECOMMENDED $234,601 $209,281 $27,089
544,254
kWh
$2,145
-
kW-mo/yr
$377
-
Tgal
$75 $204,915
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs