ITAC Assessment: UF0243
ITAC logo
ITAC Assessment: UF0243
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Automotive Parts
NAICS
n/a
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $50
M
to 100
M
# of Employees 490
Plant Area 280,000
ft2
Annual Production 1,645,000
units
Production Hrs. Annual 5,640
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,031,971 12,384,232
kWh
Electricity Demand $2,106 25,268
kW-mo/yr
Natural Gas $51,838 21,674
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $67,505 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $66,876

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,393 - $6,393
189,039
kWh
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $15,494 - $14,592
347,304
kWh
$902
-
kW-mo/yr
- - -
03 2.4133: Use most efficient type of electric motors $629 - $627
14,654
kWh
$2
-
kW-mo/yr
- - -
04 2.6231: Utilize controls to operate equipment only when needed $24,816 - - - $24,816
-
Tgal
- -
05 2.3212: Optimize plant power factor $2,493 - - - - - $2,493
06 4.425: Eliminate/reduce redundant inspections $17,680 - - - - $17,680 -
TOTAL RECOMMENDED $67,505 - $21,612
550,997
kWh
$904
-
kW-mo/yr
$24,816
-
Tgal
$17,680 $2,493
TOTAL IMPLEMENTED $66,876 - $20,985
536,343
kWh
$902
-
kW-mo/yr
$24,816
-
Tgal
$17,680 $2,493
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs