| Assessment Year | 1999 |
|---|---|
| Principal Product | Car Care and Performance Chemicals |
| NAICS |
n/a
|
| SIC | 2842: Specialty Cleaning, Polishing, and Sanitation Preparations |
| Sales Range | $10 M to 50M |
| # of Employees | 115 |
| Plant Area |
270,000
ft2
|
| Annual Production | 2,040,000
pieces
|
| Production Hrs. Annual | 5,616
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $86,964 | 1,950,176 |
kWh
|
$0.045 |
| Electricity Demand | $24,386 | 5,383 |
kW-mo/yr
|
$4.53 |
| LPG | $7,552 | 564 |
MMBtu
|
$13.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $82,592 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,710 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,463 | $17,721 |
$5,374
78,253
kWh
|
$89
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.8121: Apply for tax-free status for energy purchases | $14,710 | $50 | - | - | $14,710 | - | - | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,864 | - |
$3,864
63,306
kWh
|
- | - | - | - | - | - | |
| 04 | 2.6232: Install set-back timers | $703 | $1,240 |
$703
16,706
kWh
|
- | - | - | - | - | - | |
| 05 | 2.2221: Use immersion heating in tanks, melting pots, etc | $10,358 | $25,000 | - | - | - |
$10,358
-
MMBtu
|
- | - | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $8,015 | $5,980 |
$7,904
137,163
kWh
|
$111
-
kW-mo/yr
|
- | - | - | - | - | |
| 07 | 3.4155: Meter waste water | $3,063 | $1,500 | - | - | - | - |
$3,063
-
Tgal
|
- | - | |
| 08 | 3.3122: Use filtration, centrifuging to remove contaminants | $34,439 | $50,000 | - | - | - | - | - |
$34,439
-
gal
|
- | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,977 | $1,200 |
$641
13,482
kWh
|
$7
-
kW-mo/yr
|
- | - | - | - | $1,329 | |
| TOTAL RECOMMENDED | $82,592 | $102,691 |
$18,486
308,910
kWh
|
$207
-
kW-mo/yr
|
$14,710 |
$10,358
-
MMBtu
|
$3,063
-
Tgal
|
$34,439
-
gal
|
$1,329 | ||
| TOTAL IMPLEMENTED | $14,710 | $50 | - | - | $14,710 | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs