Assessment Year | 1999 |
---|---|
Principal Product | Archery Equipment |
NAICS |
n/a
|
SIC | 3949: Sporting and Athletic Goods, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
154,175
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $158,015 | 3,249,121 |
kWh
|
$0.049 |
Electricity Demand | $48,118 | 10,976 |
kW-mo/yr
|
$4.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,257 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,769 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7444: Close holes and openings in building such as broken windows | $5,948 | $40 |
$5,948
106,389
kWh
|
- | - | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $2,084 | $5,604 |
$1,615
32,825
kWh
|
$469
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.3191: Use demand controller or load shedder | $2,102 | $5,000 | - |
$2,102
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.1332: Convert combustion equipment to burn natural gas | $4,202 | $14,000 |
$3,822
77,960
kWh
|
$1,577
-
kW-mo/yr
|
$(-1,197.0)
-
MMBtu
|
- | - | - | |
05 | 3.5316: Contract a wood pallet recycling company | $2,615 | - | - | - | - |
$2,615
-
lb
|
- | - | |
06 | 4.521: Clear and rent existing space | $21,236 | $2,240 | - | - | - | - | $21,236 | - | |
07 | 4.652: Replace existing equipment with more suitable substitutes | $6,070 | - | - | - | - | - | - | $6,070 | |
TOTAL RECOMMENDED | $44,257 | $26,884 |
$11,385
217,174
kWh
|
$4,148
-
kW-mo/yr
|
$(-1,197.0)
-
MMBtu
|
$2,615
-
lb
|
$21,236 | $6,070 | ||
TOTAL IMPLEMENTED | $10,769 | $5,604 |
$1,615
32,825
kWh
|
$469
-
kW-mo/yr
|
- |
$2,615
-
lb
|
- | $6,070 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs