ITAC Assessment: UF0222
ITAC logo
ITAC Assessment: UF0222
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Archery Equipment
NAICS
n/a
SIC 3949: Sporting and Athletic Goods, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 154,175
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 5,200
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $158,015 3,249,121
kWh
Electricity Demand $48,118 10,976
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,257 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,769

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7444: Close holes and openings in building such as broken windows $5,948 $40 $5,948
106,389
kWh
- - - - -
02 2.4133: Use most efficient type of electric motors $2,084 $5,604 $1,615
32,825
kWh
$469
-
kW-mo/yr
- - - -
03 2.3191: Use demand controller or load shedder $2,102 $5,000 - $2,102
-
kW-mo/yr
- - - -
04 2.1332: Convert combustion equipment to burn natural gas $4,202 $14,000 $3,822
77,960
kWh
$1,577
-
kW-mo/yr
$(-1,197.0)
-
MMBtu
- - -
05 3.5316: Contract a wood pallet recycling company $2,615 - - - - $2,615
-
lb
- -
06 4.521: Clear and rent existing space $21,236 $2,240 - - - - $21,236 -
07 4.652: Replace existing equipment with more suitable substitutes $6,070 - - - - - - $6,070
TOTAL RECOMMENDED $44,257 $26,884 $11,385
217,174
kWh
$4,148
-
kW-mo/yr
$(-1,197.0)
-
MMBtu
$2,615
-
lb
$21,236 $6,070
TOTAL IMPLEMENTED $10,769 $5,604 $1,615
32,825
kWh
$469
-
kW-mo/yr
- $2,615
-
lb
- $6,070
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs