ITAC Assessment: UF0217
ITAC logo
ITAC Assessment: UF0217
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Daily newspaper and other publications
NAICS
n/a
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $10
M
to 50
M
# of Employees 293
Plant Area 70,000
ft2
Annual Production 70,000
pieces
Production Hrs. Annual 4,380
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $228,970 3,753,517
kWh
Electricity Demand $39,202 7,353
kW-mo/yr
Natural Gas $8,589 1,628
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $68,426 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $44,417

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,327 $1,400 $2,327
48,945
kWh
- -
02 2.4133: Use most efficient type of electric motors $378 $3,641 $331
5,569
kWh
$47
-
kW-mo/yr
-
03 2.2622: Replace existing chiller with high efficiency model $4,574 $6,750 $3,806
62,427
kWh
$768
-
kW-mo/yr
-
04 2.6231: Utilize controls to operate equipment only when needed $41,712 $39,500 - - $41,712
05 3.4155: Meter waste water $1,261 $1,500 - - $1,261
06 4.812: Apply for investment incentives $18,174 $50 - - $18,174
TOTAL RECOMMENDED $68,426 $52,841 $6,464
116,941
kWh
$815
-
kW-mo/yr
$61,147
TOTAL IMPLEMENTED $44,417 $44,541 $2,658
54,514
kWh
$47
-
kW-mo/yr
$41,712
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs