| Assessment Year | 1997 |
|---|---|
| Principal Product | Doughnuts |
| NAICS |
n/a
|
| SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
| Sales Range | $1 M to 5M |
| # of Employees | 55 |
| Plant Area |
7,800
ft2
|
| Annual Production | 24,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $31,721 | 647,421 |
kWh
|
$0.049 |
| Electricity Demand | $12,040 | 1,378 |
kW-mo/yr
|
$8.74 |
| Natural Gas | $22,885 | 3,203 |
MMBtu
|
$7.14 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $11,089 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,145 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,139 | $2,865 |
$1,765
36,049
kWh
|
$374
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $82 | $82 |
$56
1,172
kWh
|
$26
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.5125: Size air handling grills/ duct/s coils to minimize air resistance | $152 | $680 |
$38
879
kWh
|
- |
$114
-
MMBtu
|
- | - | - | |
| 04 | 2.7261: Install timers and/or thermostats | $221 | $200 |
$221
4,396
kWh
|
- | - | - | - | - | |
| 05 | 2.2437: Recover waste heat from equipment | $2,415 | $4,600 |
$1,975
40,445
kWh
|
$440
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,392 | $1,300 | - | - | - |
$1,392
-
Tgal
|
- | - | |
| 07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,238 | - | - | - | - | - | $(-720.0) | $3,958 | |
| 08 | 2.8121: Apply for tax-free status for energy purchases | $1,450 | - | - | - | - | - | $1,450 | - | |
| TOTAL RECOMMENDED | $11,089 | $9,727 |
$4,055
82,941
kWh
|
$840
-
kW-mo/yr
|
$114
-
MMBtu
|
$1,392
-
Tgal
|
$730 | $3,958 | ||
| TOTAL IMPLEMENTED | $3,145 | $1,582 |
$277
5,568
kWh
|
$26
-
kW-mo/yr
|
- |
$1,392
-
Tgal
|
$1,450 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs